Emmerson PLC (LSE:EML) said the arbitral tribunal hearing its US$1.215bn treaty claim against Morocco has rejected the state's request to deal with Jurisdiction separately, leaving a single final hearing scheduled for July 2028.

What was announced

Emmerson (LSE:EML), the AIM-quoted company behind the Khemisset potash project in Morocco, published unaudited interim results for the six months to 30 June 2026 on 28 September 2026. The company's focus has moved from developing Khemisset to pursuing international arbitration, following the rejection of the project's environmental permit application in October 2024, which Emmerson describes as a "total expropriation" of the project.

The claim is brought under the United Kingdom-Morocco Bilateral Investment Treaty. Emmerson submitted its Memorial on 27 March 2026, claiming damages of US$1.215bn, a figure the company says is net of local taxes and includes interest.

Morocco applied to have its jurisdictional objections heard separately from the merits of the case, a process known as bifurcation. After a hearing on 19 June 2026, the tribunal rejected that application on 17 July 2026. As a result, jurisdiction and merits will be addressed together at the final hearing.

Arbitration timetable and funding

The procedural timetable set out in the announcement is:

  • Morocco's Counter-Memorial: January 2027
  • Emmerson's Reply: October 2027
  • Morocco's Rejoinder: January 2028
  • Final hearing: 17 to 26 July 2028

The case is supported by a Capital Provision Agreement signed on 2 January 2025, which provides up to US$11.0m for litigation costs and working capital. The funding is non-recourse, meaning it does not have to be repaid if the claim fails. In return, the funder would receive an entitlement based on multiples of the amounts advanced or a percentage of any proceeds. During the half, US$1.635m was advanced under the facility, and US$1.252m of litigation costs were unpaid at 30 June 2026.

Separately, the UK Intellectual Property Office granted Emmerson Patent number 2634094 in June 2026, covering the processing of evaporite minerals and protecting its Khemisset Multi-mineral Process and related derivative products.

The numbers

The operating loss for the half widened to US$1.777m from US$1.284m a year earlier, reflecting higher legal expenses of US$2.341m, compared with US$1.004m. These costs were partly offset by other income of US$1.635m linked to the litigation funding, up from US$727,000. Administrative expenses were US$1.049m, of which US$938,000 was professional and consultancy fees. Related party disclosures show fees of US$201,000 to director Graham Clarke and US$40,000 to director Hayden Locke for the period.

Total comprehensive loss was US$1.785m (H1 2025: US$1.358m), and the loss per share was 0.14 cents (0.10 cents). Cash at 30 June 2026 was US$443,000, down from US$573,000 a year earlier and US$650,000 at the end of 2025. Net liabilities increased to US$1.101m from US$355,000 at 31 December 2025.

In March 2026 Emmerson raised about US$1.0m through a £750,000 placing and subscription and a £100,000 WRAP retail offer. The proceeds were earmarked for site remediation, engineering invoices and legal case preparation.

The board said the Going Concern basis remains appropriate, citing a Cash Flow forecast to December 2027, the funding facility, and the absence of material planned financial commitments for at least 12 months. Cash stood at US$891,000 on 9 September 2026.

What to watch next

With bifurcation refused, the next formal step is Morocco's Counter-Memorial, due in January 2027, followed by further written submissions through January 2028 and the hearing in July 2028. The announcement does not give a date for a final award, and the outcome of the arbitration is not known. Investors may also track use of the remaining capacity under the US$11.0m Facility as costs build towards the hearing.