Galileo Resources (LSE:GLR) has completed 23 holes at the Molefe copper project in Zambia, extending mineralisation eastwards to an estimated 1,310m of strike and handing a mine development plan and schedule to partner Jubilee Metals Group.
What was announced
Galileo Resources PLC, the AIM-quoted explorer, released a drilling update for the Molefe project in Zambia on 29 October 2026. The programme was carried out under a co-operation and project development agreement dated 27 November 2025 with Jubilee Metals Group PLC, which operates the Molefe mine.
The drilling had three purposes: to test the shape and continuity of mineralisation on the eastern limb of the ore zone, to confirm mineable tonnes, and to condemn ground for future infrastructure. Galileo described the information as inside information under UK MAR.
The numbers
Galileo drilled nine holes totalling 552.6m to test continuity and mineralisation, and 14 condemnation holes totalling 1,298.9m, giving about 1,851.5m across 23 holes. The condemnation holes ranged from 44.2m to 206.2m in end-of-hole depth.
Intercepts were reported using a minimum mineralised width of 3.0m and a 0.4% total copper (TCu) cut-off. The highest grade was 3.10m at 2.97% TCu from 57.6m in hole MNKDD021. The widest high-grade intervals were 12.5m at 1.51% TCu from 26.4m in MNKDD029 and 10.5m at 1.24% TCu from 12.5m in MNKDD027.
Other holes returned 13.0m at 0.87% TCu from 22.0m in MNKDD024, 11.1m at 0.84% TCu from 9.3m in MNKDD033 and 7.00m at 0.57% TCu from 64.0m in MNKDD025. MNKDD026 intersected two zones, 7.70m at 0.45% TCu from 18.3m and 6.95m at 0.74% TCu from 29.05m, while MNKDD030 returned 5.00m at 0.42% TCu from 49.0m.
The work increased the strike length of mineralisation by about 380m to an updated estimate of 1,310m, compared with 930m previously, with the extension running to the east.
Galileo has provided a mine development plan and schedule to Jubilee for its consideration. The schedule targets an oxide copper reef of about one million tonnes at a grade of at least 1.30% TCu, including about 240,000 tonnes at 1.45% TCu in pits 2 and 3, which are the immediate targets. The eastern extension identified by this programme is not included in the schedule. The company stated that the drilling results and in-pit sampling do not represent a resource estimate under any standard.
Condemnation work and partnership
The 14 condemnation holes identified areas within the licence suitable for waste rock disposal, tailings storage and a processing plant. This type of drilling is used to check that planned infrastructure will not sit on top of ground that could later be mined.
The announcement does not disclose the economic terms of the collaboration agreement with Jubilee, nor any ownership or profit-sharing percentages attributable to Galileo. Jubilee, in its own announcement the same day, described Galileo as responsible for mine planning and resource definition under the partnership.
Chairman Colin Bird, who also acts as Qualified Person and has more than 40 years of mining experience, mainly in hard rock, said the company was "pleased to be able to increase the strike length of mineralisation". He added that the data had informed a mine development plan and infrastructure planning.
What to watch next
The mine development plan and schedule now rest with Jubilee. Galileo did not give a timeline for Jubilee's decision or set out a next phase of drilling. Jubilee said in its parallel update that it is targeting an updated resource calculation including the Phase 2 results by the end of calendar 2026.
For Galileo's shareholders, the key unknowns remain the commercial terms of the arrangement and how any future production at Molefe would translate into value for the company, neither of which was addressed in the release.