Key Highlights

  • Greatland produced 328,987oz of gold plus 14,594t of copper in FY2026 at an AISC of ~A$2,179/oz, beating guidance.
  • It ended the year with A$1.289bn of cash, debt-free, and total Liquidity of about A$1,764m.
  • The board approved the Havieron final Investment decision in June 2026; construction to start shortly, first gold targeted ~FY2029 (~2.5 years).
  • Group ore reserves rose 62% to 5.0Moz of gold, led by a 150% increase at Telfer to 1.8Moz.
  • FY2027 guidance is 260,000-300,000oz at a higher AISC of A$2,900-3,330/oz, with ~A$780-850m of growth Capital planned.

Greatland (LSE:GGP) Resources has moved decisively from turnaround story to growth builder. In the space of a single year the company, which owns the Telfer mine and the Havieron deposit in Western Australia's Paterson Province, beat its maiden production guidance, amassed a large cash pile and sanctioned the development that underpins its long-term ambitions.

The dual-listed group – trading on London's AIM and the ASX under GGP after acquiring full ownership of Telfer and Havieron from Newmont – now presents investors with a rare combination for a young producer: a mine throwing off cash today and a sizeable, funded growth project alongside it. The June 2026 results and the Havieron final investment decision crystallise that story.

Latest Development

The pivotal event is the Final Investment Decision (FID) for the Havieron underground gold-copper project, approved by Greatland's board in June 2026. The primary decline boxcut has been completed, secondary approvals were expected within weeks, and construction is set to commence thereafter, with first gold targeted approximately 2.5 years from the start of construction – pointing to around FY2029. Pre-production capital is estimated at about A$1,065m (base date June 2025).

Havieron is being sanctioned from a position of strength. Greatland exited FY2026 with A$1.289bn of cash and no debt, having beaten its full-year production guidance. Alongside the operating momentum, the company delivered a major reserve upgrade – lifting group ore reserves by 62% – that materially extends and de-risks the Telfer-Havieron growth plan.

The Numbers

For the year to 30 June 2026 (reported 29 July 2026), Greatland produced 328,987 ounces of gold plus 14,594 tonnes of copper at an All-In Sustaining Cost of about A$2,179 per ounce, comfortably beating guidance of 260,000-310,000 ounces at an AISC of A$2,400-2,800. The June quarter alone delivered 79,100 ounces, and Q4 gold sales of 74,648 ounces at a weighted-average realised price of around A$6,468 per ounce generated roughly A$545m of net revenue. The company added about A$714m of cash over the year and reported total liquidity of around A$1,764m including undrawn facilities.

The reserve story is equally striking. Group ore reserves rose 62% to 5.0 million ounces of gold (with associated copper), driven primarily by Telfer, where reserves grew 1.1 million ounces to 1.8 million ounces – a 150% increase since March 2026 – including a 375% jump at the West Dome open pit and a maiden Main Dome underground reserve. Havieron's reserve stands at 3.3 million ounces of gold and 128,000 tonnes of copper.

The Investment Story

Greatland's investment case rests on two complementary Assets in a tier-one Mining jurisdiction. Telfer, a large, previously mothballed operation Greatland has restarted and expanded, is the cash engine – generating the free Cash Flow that funds growth and, crucially, that has been extended by the recent reserve upgrade into a multi-year base-load producer. Havieron is the long-life growth engine: a high-grade underground gold-copper deposit that will be developed as a linked operation feeding processing infrastructure in the district.

The strategic logic is to convert strong current gold prices and Telfer's cash generation into a larger, longer-life production base without stretching the balance sheet. With no debt, over A$1.2bn of cash and access to Credit facilities, Greatland is unusually well funded for a company of its size to self-finance a major build. Continued exploration success in the Paterson Province offers further upside, and the copper by-product adds exposure beyond gold.

What Could Drive the Shares?

Near-term catalysts include the formal start of Havieron construction once secondary approvals are received, and steady delivery against FY2027 guidance. Continued reserve and resource growth from the intensive FY2027 drilling programme could further extend mine life and support the valuation. A sustained high gold price would amplify Telfer's cash generation, while progress and cost control on the Havieron build – keeping it on the roughly 2.5-year timeline to first gold – would validate the growth thesis. Any move to formalise capital returns from the strong cash position could also attract income-focused interest.

Risks Investors Should Watch

The principal risks are execution and cost. FY2027 AISC guidance of A$2,900-3,330 per ounce is materially higher than FY2026, reflecting lower-grade stockpile feed, and unit costs will bear watching. The Havieron build is a large, multi-year underground project carrying the usual schedule, Inflation and grade-reconciliation risks, with meaningful capital to deploy before first gold around FY2029. Group Earnings remain highly leveraged to the gold price, and to a lesser extent copper.

What Happens Next?

Watch first for receipt of Havieron secondary approvals and the official commencement of construction, expected within weeks of the FY2026 report. Beyond that, quarterly production reports will show delivery against FY2027 guidance and stockpile management at Telfer, while the FY2027 drilling campaign should generate further reserve and resource updates. Progress milestones on the Havieron decline and development schedule, and any commentary on future capital allocation given the large cash balance, will be the key markers through the coming year.

Bottom Line

Greatland (LSE:GGP) has turned a restarted mine into a cash machine and used that strength to sanction a major growth project, all while lifting reserves 62% and staying debt-free with A$1.29bn in the bank. The bull case is a self-funded transition to a larger, longer-life gold-copper producer; the risks are rising unit costs, execution on the Havieron build and reliance on a firm gold price. For now the delivery has matched the ambition, but the Havieron construction phase is where the story will be proved.

What to Watch

  • Receipt of Havieron secondary approvals and the formal start of construction.
  • Delivery against FY2027 production and AISC guidance amid lower-grade stockpile feed.
  • Reserve and resource updates from the intensive FY2027 drilling campaign.
  • Havieron development schedule and capital-cost control through to first gold (~FY2029).
  • Gold and copper prices, and any decision on capital returns from the large cash balance.