GreenRoc Strategic Materials says laboratory testing of a 300kg subsample from its Amitsoq bulk sample in Greenland produced a 95.2% graphite concentrate with recovery above 90%. The figure comes from a replacement announcement that corrected the concentrate grade from the 92.3% first stated.
What was announced
On 29 September 2026 GreenRoc Strategic Materials Plc (LSE:GROC) issued an update on its Amitsoq Graphite Project in Greenland. Later the same day it published a replacement announcement correcting one figure: the graphite concentrate grade was revised from 92.3 wt.% to 95.2 wt.%. The company said all other information was unchanged.
The results come from SGS Lakefield in Canada, which tested a 300kg subsample of a 20-tonne bulk sample. The company reported:
- head grade: 22.3 wt.% graphite
- concentrate grade: 95.2 wt.% graphite
- recovery: over 90%
Testing began in April 2026. It involved crushing the material to below 3.35mm, followed by 20 flotation tests and locked-cycle testing to validate the processing flowsheet.
Chief Executive Stefan Bernstein said the laboratory results demonstrate high graphite recovery and high-grade concentrate, providing important validation of Amitsoq's processing potential.
The bulk sample and next processing stage
The 20-tonne bulk sample was taken from the Lower Graphite Layer at two sites located 50 metres and 100 metres from the mine entrance. About 18 tonnes were extracted in October 2025 and a further 2 tonnes were collected from the same location in August 2026.
The full sample will be shipped to GTK Mintec's Facility in Outokumpu, Finland. GreenRoc expects results before the end of 2026, covering comminution and flotation performance and the production of several tonnes of graphite concentrate. That concentrate is intended as feedstock for the company's pilot plant in Denmark for active anode material (AAM), a component of lithium-ion batteries.
The SGS result is based on a 300kg subsample, a small fraction of the full bulk sample; based on the disclosed figures, it represents 1.5% of the 20 tonnes. The GTK Mintec work will test the process at a larger scale.
Underground survey and drilling
The company also reported on a September 2026 survey of the historical underground workings:
- Level A, 17 metres above the high-water mark, is accessible through two portals and was surveyed using a scanning total station and LiDAR. It was developed within the Lower Graphite Layer and showed few stability issues, needing little rehabilitation beyond the removal of scrap metal.
- Level B, 2 metres above the high-water mark, is partly flooded. Its one accessible portal shows stability issues, only partial LiDAR data was acquired, and the portal needs clearing and ground support.
- Level C, 13 metres below sea level, is currently inaccessible. A flooded inclined shaft reportedly extends 20 metres below sea level, and the extent of the level is unknown.
A 3D model is being built to support orebody modelling and mine planning.
The final two holes of the Phase III drilling programme are due to resume in the week of 5 October 2026, with completion targeted by 16 October 2026. The company said the delay was caused by limited helicopter availability.
Background and what to watch next
GreenRoc (LSE:GROC) states that Amitsoq has a combined Measured, Indicated and Inferred JORC resource of 23.05 million tonnes at an average grade of 20.41% graphite, which it says is sufficient for more than 20 years of mining. It received an Exploitation Licence in December 2025 for a 30-year term.
The next milestones set out by the company are completion of the Phase III drilling by mid-October 2026 and the GTK Mintec processing results before the end of 2026. The announcement contains no financial information or funding update.