Harena (LSE:HREE) Rare Earths, formerly Harena Resources, reported a pre-tax loss of £5.2 million for the period to 30 June 2026, down from £14.2 million, during which it took full ownership of its Ampasindava project and later formalised an exploitation permit in Madagascar.
What was announced
Harena (LSE:HREE) Rare Earths PLC, previously named Harena Resources PLC, released its annual results on 30 October 2026. The accounts cover a 14-month period ending 30 June 2026, although the financial statements and chairman's statement refer to the year ended 30 June 2026. The comparative is the year to 30 June 2025, and the 2025 Balance Sheet has been restated. The financial statements were approved on 30 October 2026.
The company is developing the Ampasindava rare earths project in Madagascar.
The numbers
Loss before tax was £5,164,015, compared with £14,187,288 in the prior period. The prior-period figure included listing costs of £10,321,369, with no such costs this time. The operating loss rose to £5,070,957 from £3,330,754. Total comprehensive loss was £5,036,148 (prior: £14,138,511) and the loss per share was 0.88p (prior: 10.82p).
Cash and cash equivalents increased to £1,105,169 from £28,425. Total Assets rose to £3,466,506 (prior: £2,100,482), including exploration-related intangible assets of £2,192,501. Net assets were £2,187,434, up from £915,231, and the group carried a Loan note Liability of £677,654.
In Cash Flow terms, the operating outflow was £2,060,861, Investment in exploration assets was £142,916 and financing inflows totalled £3,326,471. The Parent Company recorded a loss of £4,516,303.
Project and corporate developments
In August 2025, Harena (LSE:HREE) restructured its holding in Ampasindava, removing a 25% minority interest so that it now owns 100% of the project. A Pre-Feasibility Study completed in January 2026 gave what the company calls an indicative route to production, and work has since moved to a Definitive Feasibility Study (DFS) and an environmental and social impact assessment (ESIA).
On 30 January 2026, Madagascar's government lifted a 16-year moratorium on new Mining permits across most mineral categories, including rare earths. Harena (LSE:HREE) signed the Cahier des Charges Minières on 11 August 2026, and its Exploitation Permit was announced as formalised on 12 October 2026. The company is now seeking an Environmental Permit and completing Environmental and Social Management Plans, which are required before pilot-phase infrastructure can be built.
On 21 July 2026, Harena (LSE:HREE) signed a Project Development Funding Agreement under which the U.S. International Development Finance Corporation (DFC) committed US$4.84 million towards permitting and environmental and social studies for a proof-of-concept plant. The DFC announced the financing on 7 and 10 August 2026.
Equity funding during the period included about £1.2 million from an institutional placing and subscription in August 2025, £450,000 from RAB Capital in October 2025 and £2.0 million from Greg Coffey and Matthew Press in February 2026. The shares began trading on the OTCQB in the United States in November 2025.
Board changes included Ivan Murphy becoming Executive Chairman from 1 October 2025, Paul Richards joining as a Non-Executive Director, and Cameron Pearce and Sam Quinn stepping down. Jack Allardyce was appointed interim CFO in January 2026 and confirmed in the role in April 2026.
What to watch next
Mr Murphy said: "We enter the new financial year with real momentum and a clear path towards production." The company's stated priorities are to progress the DFS and ESIA, complete outstanding environmental permitting and advance towards construction of a Demo Plant. No construction timetable or cost estimate was given, and the material reviewed did not include a mineral resource update or an AGM date. The full report and accounts will be posted to shareholders shortly and are available on the company's website and the National Storage Mechanism.