Jubilee Metals Group (LSE:JLP) has spent 2026 turning itself into a focused copper Business in Zambia, selling South African Assets and non-core projects while ramping up its own Mining operations. In a production and operational update on 14 September 2026, the company reported combined copper production before refining of 3,739 tonnes for the year to 30 June 2026, up 225% from about 1,150 tonnes a year earlier.
The update followed news on 26 August 2026 that Jubilee had selected a preferred purchaser for its Large Waste Project in Zambia, in a deal valued at US$35.0m, or US$30.0m if the buyer chooses to settle within two years.
What Jubilee Metals Does
Jubilee is dual-listed on AIM and the AltX of the Johannesburg Stock Exchange. Its Zambian copper business is built around the Roan concentrator, which processes third-party feed, the Sable refinery, the Molefe mine, which the company owns, and Project G, its next planned mining project. On 2 January 2026, Jubilee completed the sale of its South African chrome and platinum group metals operations to One Chrome, keeping only its interest in the Tjate platinum project, which is now the subject of a strategic review.
Latest Developments
Roan produced 2,823 tonnes of copper in FY2026, up 145.5%, while Sable produced 1,207 tonnes of cathode, up 17.5%. Molefe began production in September 2025 and delivered 916 tonnes of copper units, of which 345 tonnes of high-grade material was sent to Sable and the rest stockpiled. The company said fourth-quarter output at Sable was hit by lower domestic acid availability, with acid costs rising by more than 200% and diesel costs by 90%.
For FY2027, Jubilee guided Roan to produce 2,850 to 3,150 tonnes of contained copper. It has not yet set formal guidance for Molefe and expects to do so once stable operation is shown, which it currently anticipates before the end of calendar 2026. Development of Project G is targeted from February 2027.
Financial Picture
Under the Large Waste Project sale, the buyer will pay US$2.25m, subject to completing an initial Due Diligence stage, to secure a further 45 days of exclusivity, with the balance paid over three years. In its 10 August announcement, Jubilee said total cash inflows from the South African sale and non-core waste asset disposals were nearing US$100m. Separately, the original seller of the project elected to take its final US$5.0m payment in shares, with about 150.5 million new shares issued at 2.5p each.
In May 2026, Jubilee agreed an initial US$1.5m convertible Loan note with an investor that had helped develop Mantos Copper, with a possible further US$10m under discussion but not certain. No Dividend information was found in recent announcements.
Sector and index Context
Jubilee is among several mining companies in the FTSE AIM All Share Index seeking to benefit from Demand for copper, which is used heavily in electrification and power networks. Zambia is one of Africa's largest copper producers, but its operating costs, power and reagent Supply can be challenging.
Key Risks
Rising acid and diesel costs have already affected output. Molefe has yet to demonstrate stable production, and Project G remains at an early stage. The Large Waste Project sale is still subject to due diligence and definitive agreements, and staged payments carry counterparty risk. Share issues to fund growth or settle obligations may dilute existing shareholders.
What to Watch Next
Investors will watch for completion of the Large Waste Project sale, formal Molefe guidance, the outcome of the Tjate review and further copper output updates.