Bridging the gap between two mines

Metals Exploration (LSE:MTL) has released no announcements between 12 and 16 November 2026; its most recent was a notice on 2 November of share Options exercised by its chairman. The latest operating information is the quarterly update to 30 September, published on 27 October. This article looks at a different detail: how the company plans to keep its Philippine mine, Runruno, working until the Nicaraguan project starts producing.

Low-grade material made economic

After reviewing historical stockpiles, the company identified about 740,000 tonnes of material that was below the economic cut-off grade when it was mined. That comprises marginal ore grading 0.45 to 0.55 grammes of gold per tonne and mineralised waste at 0.3 to 0.45 g/t. Metals Exploration (LSE:MTL) said the much higher gold price had made it worth processing. The material is already drilled and blasted, sitting on the run-of-mine pad or mostly inside the pit, so it can be dug freely and rehandled.

The company (LSE:MTL) plans to run this campaign until the end of January 2027, extending Runruno's life to that point, and said the timetable would be reviewed and could lengthen if conditions remain favourable.

Putting the numbers in context

740,000 tonnes at grades between 0.3 and 0.55 g/t would contain roughly 7,000 to 13,000 ounces before recovery losses. The company did not give a contained-ounce estimate. For comparison, Runruno milled 572,000 tonnes in the third quarter, so the stockpiles represent a little over one quarter of plant throughput, consistent with the January end date.

The grade gap is significant. Third-quarter head grade was 0.89 g/t, producing 14,108 ounces at a Recovery Rate of 86.3%. Material grading half that would Yield fewer ounces for similar Mining and processing effort, which implies higher costs per ounce than the third quarter's All-In Sustaining Cost of US$1,883.

Grades have been falling for some time. Over the first nine months of 2026, the average milled grade was 0.88 g/t against 1.27 g/t a year earlier, while the realised gold price averaged US$4,520 against US$2,885. It is that price rise, rather than better geology, that has made the stockpiles worth treating.

A solid quarter as the base

Runruno sold 13,500 ounces in the quarter at an average of US$4,273, generating Revenue of US$57.7m and pre-tax free Cash Flow of US$34.5m. Cash rose to US$31.8m from US$9.0m at the end of June. The company expects 2026 output at the upper end of its 40,000 to 48,000-ounce guidance, having produced 35,559 ounces in nine months. It has also fully drawn a US$27m equipment Loan and forward-sold 2,000 ounces for delivery in the fourth quarter.

Why the bridge matters, and the factors to watch

La India was 75% complete, with spending of US$152.3m against a revised forecast of US$186m. First gold slipped to the first quarter of 2027 from December after low-voltage cabling was stolen in transit through Costa Rica; replacement has a lead time of about six weeks. Construction is funded by Runruno, so any overlap between the two mines reduces reliance on borrowings.

Risks include lower recoveries from marginal material, gold price movements that could make the stockpiles uneconomic again, and further delay at La India. A contractor's employee died at the site on 19 October; work resumed on 21 October after a safety stand-down, and the company-led investigation continues.

What to watch

Key markers are the fourth-quarter update, any decision to extend Runruno beyond January, and the first gold pour at La India. No dates for those disclosures have yet been announced. In addition, the final spillway at Runruno's residual storage impoundment, which the company expected to complete by the end of October, is another item the company's next quarterly update should confirm.