Pensana's update of 25 September 2026 dealt with two related questions: how its Longonjo rare earth mine in Angola will be funded, and what the company plans to do with a nearby exploration project at Coola. The answer on Coola is to bring in a partner that will spend money on exploration in exchange for most of the interest. This article explains the farm-in arrangement and why it comes at a time when the company is waiting for its main strategic funding to arrive.
Pensana and Longonjo
Pensana (LSE:PRE) is a rare earths developer whose shares trade on the Main Market of the London Stock Exchange under the ticker PRE. Its core asset is the Longonjo project in Angola, which, according to its interim report, targets 2,400 tonnes a year of neodymium-praseodymium (NdPr), used in permanent magnets, together with 73 tonnes of heavy magnet metals dysprosium and terbium, in the form of a mixed rare earth carbonate. The company also refers to a Downstream strategy, including a planned rare earth processing hub at Saltend in the UK, under its "mine to magnet" ambition.
The September update
On 25 September 2026, Pensana said Longonjo construction was more than 30% complete, but that high-cost site activities had been reduced while financing was finalised, and completion was now expected in late 2028. Debt facilities involve ABSA and EXIM. Of a US$165 million strategic Investment committed by Cascade Natural Resources, a vehicle backed by the State of Qatar, US$15 million had been received.
On Coola, an exploration project about 30 km from Longonjo, the company announced a farm-in by Tyranna, which is listed on the Australian Securities Exchange. Tyranna is to spend US$2.6 million over three years with a view to reducing Pensana's interest to 20%. Pensana said that if a mine is successfully developed at Coola, "the option remains for the mine product to be treated at Longonjo". This suggests the arrangement allows exploration to continue without Pensana committing its own scarce capital, while preserving a potential source of future feed for its processing plant.
Funding background
The Cascade investment has been slower to arrive than planned. In an update on 6 August 2026, chairman Paul Atherley said delays in funds transfer were "frustrating and will impact on the Longonjo project development schedule in the short term". That update also said the scope of the investment had been widened to support the downstream strategy and a proposed Nasdaq listing. On 17 August 2026, Pensana said that the appointment of a Cascade nominee to its board was not yet effective.
Interim results for the six months to 31 December 2025, published on 27 March 2026, showed a loss of US$4.5 million, cash of US$19.6 million and net Assets of US$96.9 million, with US$72.3 million of Longonjo costs capitalised. The directors noted a material uncertainty linked to deploying remaining construction funding and settling a US$8.7 million bridging loan.
Risks and what to watch
The key risk remains funding for Longonjo. Until the remaining US$150 million from Cascade is received, construction pace will stay restricted and the timetable could move again. Rare earth prices, Angolan operating conditions and the cost of restarting full construction add further uncertainty. For Coola, exploration results are not assured, and Pensana's interest would be diluted to a minority. Receipt of further Cascade tranches and confirmation of debt arrangements are the main milestones over the coming months.
Conclusion
Pensana is farming out Coola so that a partner funds exploration while it concentrates limited resources on Longonjo, keeping the option to process any future Coola output at its plant. The more important issue remains the delayed strategic funding, which will determine whether the late 2028 completion target holds.