Mining fewer tonnes but earning far more from each one is not a combination miners get to enjoy often. That was the story of the first half of 2026 for Antofagasta (LSE:ANTO), the Chile-focused copper producer and FTSE 100 constituent, as record copper prices more than made up for a weather-hit fall in production.

The group's half-year results, published on 13 August 2026, showed EBITDA up 27% and a sharply higher interim dividend, even as copper output dropped and full-year production guidance was cut. For anyone trying to understand what is driving the shares, the contrast between price and Volume is the key to the whole picture.

A snowbound mine and a booming copper price

The headline problem was Los Pelambres, Antofagasta's flagship mine high in the Andes. Severe winter weather forced a shutdown there, and on the results call management described snowfall of around five million cubic metres disrupting operations. Group copper production for the six months to 30 June came in at 285,000 tonnes, down 9% on the same period a year earlier.

As a result, the company lowered its 2026 copper production guidance to 625,000 to 655,000 tonnes. Los Pelambres has since resumed operations, and the company said it expects output to increase quarter by quarter through to the end of the year.

The counterweight was price. Copper prices reached record levels during the period, and the benefit flowed almost directly into margins. The market's initial reaction still leaned towards the production cut, however: the shares fell by almost 5% on results day, despite Earnings Per Share beating analyst forecasts.

Margins above 60% and a much bigger dividend

The financial numbers show how powerful a strong copper price can be for a low-cost producer. Revenue rose 18% to $4,479.0m, while EBITDA climbed 27% to $2,840.5m. The EBITDA Margin widened to 63.4% from 58.8% a year earlier, a level few industrial businesses of any kind achieve.

Further down the income statement the gains were even larger. Profit before tax rose 72% to $1,995.8m, and underlying earnings per share jumped 81% to 85.9 cents. This compared with a consensus forecast of roughly 75 cents, although revenue was a touch below expectations.

Costs also moved in the right direction. Net cash costs fell 8% year on year, and full-year cost guidance was left unchanged. Shareholders shared in the upswing through an Interim Dividend of 30.1 cents per share, an 81% increase that reflects the group's policy of paying out 35% of underlying earnings.

Why copper's long-term story matters for Antofagasta

Antofagasta is one of the purest ways to gain exposure to copper within the FTSE 100. Unlike the diversified giants that also mine iron ore, coal or other metals, its earnings rise and fall largely with the copper price, alongside smaller contributions from gold, molybdenum and its transport division in northern Chile.

Management is clearly confident about the longer-term backdrop. On the results call, the chief executive, Iván Arriagada, said that global copper Demand is expected to grow by approximately eight million tonnes by 2035, while Supply is expected to grow by only about four million tonnes. Electrification, grid investment, electric vehicles and data centres are all drawing on the same finite pool of new supply, and major new copper mines take many years to permit and build.

Antofagasta (LSE:ANTO) is investing to capture that opportunity. The Centinela second concentrator is in pre-commissioning, with commissioning targeted for 2027 and full ramp-up in 2028. At Los Pelambres, work continues on a concentrate pipeline and on expanding the desalination plant to 800 litres per second, reducing reliance on scarce continental water. The board has also approved around $0.9bn for a water pipeline system at Zaldívar, which the company said could support a mine life extension to 2051. The results statement stressed that the group remains "well positioned for the future with a resilient Balance Sheet and low levels of net debt."

What could knock the story off course

The first half showed how quickly operational problems can bite. A single weather event at one mine was enough to force a guidance cut, and Chile's high-altitude operations remain exposed to extreme weather, water Scarcity and occasional labour disputes. Any further disruption at Los Pelambres in the second half would put the lowered guidance range under pressure.

The bigger swing Factor is the copper price itself. Record prices flatter margins, but they also mean earnings are unusually sensitive to any pull-back driven by weaker Chinese demand, a slowdown in global Manufacturing or shifts in US trade policy. A fall in the metal price would feed straight through to EBITDA and, because the dividend is set as a share of earnings, to Shareholder payouts as well.

There are also execution and political risks. Large projects such as the Centinela concentrator can run into delays or cost overruns; geotechnical work at Centinela required additional sealing, although management said this remained within the existing budget. Chilean Royalty and tax policy has shifted in recent years and could do so again, and Investment in the US Twin Metals project continues to depend on the permitting environment.

Production updates and project milestones ahead

The next major checkpoint will be Antofagasta's third-quarter production report, which the company typically publishes in October. That will show whether Los Pelambres has recovered as quickly as management expects and whether the group is tracking towards the upper or lower end of its revised 625,000 to 655,000 tonne range.

Beyond that, the focus will be on the Centinela second concentrator as it moves towards commissioning in 2027, and on any update to 2027 production and Capital Expenditure guidance, which is normally provided around the turn of the year. Copper price moves, Chinese economic data and interest-rate expectations will continue to shape sentiment towards the shares day to day.

Conclusion

Antofagasta's first half demonstrated both sides of a pure-play copper miner. Record prices drove a 27% rise in EBITDA, margins above 60% and a much larger dividend, yet a weather-related production shortfall reminded the market that volumes can disappoint. With major projects advancing and management upbeat on long-term supply and demand, the investment case rests heavily on copper prices holding up and on the second half delivering the operational recovery the company has promised.