KEFI Gold and Copper plc has lifted the suspension of development at its Tulu Kapi gold project in Ethiopia, imposed in early September after an incident that resulted in the first injury and fatality involving company personnel in about 12 years. Work will resume in three phases, and the company says its lenders remain supportive while drawdowns are re-sequenced.

What was announced

KEFI said the suspension of development imposed on 7 September 2026 has been lifted.

The suspension followed what the company calls the "Genji Incident", which began on 4 September 2026 and concluded on 10 September 2026. According to KEFI, it was the first injury and fatality involving company personnel in roughly 12 years of the company's control of the project.

Development was suspended for a little over five weeks, from 7 September to 12 October 2026.

Executive Chairman Harry Anagnostaras-Adams said: "We are enjoying huge support from all stakeholders and are now restarting development with a phased and measured approach".

A three-phase restart

KEFI said development will resume in three phases:

1. Phase one covers electricity connections and new access roads.

2. Phase two covers replacement housing and land for people being resettled.

3. Phase three covers security infrastructure, bulk earthworks for the processing plant and the permanent workforce camp.

The ordering places infrastructure and resettlement work ahead of security installations and plant earthworks.

Funding and stakeholders

KEFI said it has invested "well over US$150 million" in the project to date.

The company said its lenders continue to support it while development sequencing and the timing of loan drawdowns are updated to reflect the phased restart. It did not name the lenders, give amounts for the facilities involved, or say whether any formal amendments to financing agreements will be required. Any change to drawdown timing is therefore described only in general terms.

The company also said it consulted the local community, the Ethiopian federal government and the government of the Oromia region before restarting. KEFI said local companies are being prioritised for work on the project and that about 1,000 local people would be employed once the mine is in production.

More broadly, Tulu Kapi has been under KEFI's control for about 12 years. The September incident and the resulting suspension interrupted development work that had been under way at the site, with the company now resuming activity on a staged basis rather than all at once. The restart announcement focuses on the sequence of work and stakeholder support rather than on changes to project economics, and does not include updated production, cost or reserve figures.