KEFI Gold and Copper's (LSE:KEFI) interim results show that development of its Tulu Kapi gold project in Ethiopia was suspended after a security incident on 4 September 2026 in which several people died. The directors have flagged a material uncertainty over the group's ability to continue as a going concern.

What was announced

KEFI, which is quoted on AIM, published its results for the six months to 30 June 2026 on 29 September 2026. The company said "a serious security incident at the Tulu Kapi Gold Project resulted in multiple fatalities, including a Company employee". Those who died included security personnel and members of the local community. KEFI said all other affected employees were accounted for and there were no further injuries. "The Company's thoughts remain with his family and with all those affected," it said.

Development work, which began in March 2026 and had been on schedule, was suspended with immediate effect. KEFI says it will resume once appropriate measures are in place, in coordination with community representatives, the Federal Democratic Republic of Ethiopia, the Oromia Regional Government and security stakeholders, "to provide a safe and secure operating environment". No date for resumption is given.

KEFI said that consultations with the community and the Ethiopian and Oromia governments had "reaffirmed support for the Project and for the Company's careful approach to resuming development". It added that its principal contractors, lenders and local investors remain supportive.

The numbers

  • Net loss: £4.6m (H1 2025: £3.1m), reflecting higher administration expenses of £4.3m (£2.4m) and £0.5m of finance Transaction Costs related to project financing.
  • Net assets: £87m at 30 June 2026 (31 December 2025: £57m).
  • Cash: £18.3m at 30 June 2026.

KEFI raised new Share Capital during 2026. It raised £7.1m in March by issuing 589m shares at 1.2p, and £27.6m in April through 2.3bn shares at 1.2p. Including smaller share issues to service providers and Warrant exercises, net proceeds totalled £34.7m after £1.9m of costs.

Background

Before the incident, KEFI said the Tulu Kapi financing was "fully assembled". The package comprised:

  • US$240m of senior secured Debt from the Eastern and Southern African Trade and Development Bank and the Africa Finance Corporation, executed on 31 March 2026;
  • US$60m of Mining fleet financing through BCM Group; and
  • more than US$100m of risk capital, including Ethiopian preference shares, royalties and Government of Ethiopia participation at the project company level.

Drawdown of the senior debt depends on the lenders being satisfied about local and regional security and political stability. KEFI holds about 86% of the project, with the Government of Ethiopia holding the balance.

The directors said the suspension creates "a material uncertainty that may cast significant doubt on the Group's and the Company's ability to continue as a going concern". They still expect activities to resume safely and funding to be secured. They cite government support, constructive talks with lenders and the company's fundraising record. KEFI says it has deferred drawdown of project financing and is managing spending closely.

Elsewhere, KEFI's stake in Saudi joint venture GMCO is now about 13%, down from 15.34%. GMCO was awarded the Umm Hijlan and Al Hajar North licences, and feasibility studies at Jibal Qutman and Hawiah continue. On the board, Richard Robinson retired, Dr Alistair Clark became Senior Independent Director and Deputy Chairman, and Maleda Bisrat and Danny Callow joined as independent non-executive directors. Stifel was appointed in May 2026 as financial adviser and joint broker ahead of a planned move from AIM to the Main Market.

What to watch next

The key disclosed dependencies are the restoration of a secure operating environment at Tulu Kapi, the lenders' position on drawdown conditions, and any change to the project timetable. KEFI (LSE:KEFI) has not given a revised schedule.