Key Highlights

  • Construction of the $340 million Tulu Kapi gold mine in Ethiopia is on schedule, with commissioning targeted for late 2027 and full production by mid-2028.
  • More than half of the mine's major equipment has been ordered, and contractors are mobilising on site.
  • Debt drawdown of the $240 million senior Facility is on track for the fourth quarter of 2026.
  • The mine plan totals around 1.215 million ounces of gold, with a modelled NPV of $710 million to $1.67 billion across a $3,000-5,000/oz gold price band.
  • KEFI's stake in its Saudi Arabian joint venture GMCO has been diluted to around 13% following a partner-funded Capital increase.

Nearly two decades after first staking its claim, LSE-listed KEFI Gold and Copper has broken ground on the $340 million Tulu Kapi gold mine in Ethiopia. Debt drawdown is due in the fourth quarter, with first production targeted for 2028.

KEFI Gold and Copper, the LSE-quoted developer behind the Tulu Kapi gold project in Ethiopia and a minority stake in Saudi Arabian exploration ventures, told investors on 4 August that construction of its flagship mine remains on schedule. Commissioning is targeted for late 2027, with full production expected by mid-2028. For a project that has waited close to twenty years to reach this stage, the update is a modest but meaningful marker that the long-delayed build is genuinely under way.

What Happened

In its 4 August operational update, KEFI reported that more than half of Tulu Kapi's major equipment has been ordered or is ready for ordering, and that contractors Lycopodium, EEP, ERA and BCM are mobilising personnel on site. Completed works include housing for resettled communities, an electrical substation and a new access road. Executive Chairman Harry Anagnostaras-Adams said "progress across community resettlement, plant procurement and construction is in line with schedule."

The update followed a groundbreaking ceremony at Tulu Kapi on 18 February, attended by the Ethiopian Prime Minister, marking the formal start of construction after KEFI completed the project's $340 million financing package: roughly $240 million of senior bank debt guaranteed by KEFI, $20 million of Ethiopian government Equity , $30 million from KEFI equity placings, a $20 million equity-ranking Royalty with Chancery Royalty Limited, and a ~$60 million services agreement for the Mining contractor's fleet. Debt drawdown is on track for the fourth quarter, and KEFI says it remains "well-funded" following earlier equity raises.

On resettlement, all Phase 1 compensation agreements have been signed, with roughly 90% of payments made, while a Phase 2 plan for the mining and plant areas is being prepared.

Why It Matters

Tulu Kapi has been one of LSE's most-delayed development stories, pushed back repeatedly by financing gaps, resettlement obligations and Ethiopia's macroeconomic and security difficulties. A confirmed construction schedule, a signed debt package and contractors on site represent a genuine inflection point rather than another paper milestone. For a stock that has traded on hope for years, execution risk is now the dominant question, not financing risk.

Scale matters too. The mine plan is around 1.215 million ounces of gold from 17 million tonnes at 2.4 grams per tonne, with a modelled net present value to KEFI, at construction start, of roughly $710 million to $1.67 billion across a $3,000-5,000/oz gold price band — figures that dwarf KEFI's £174 million Market Capitalisation , though realising them depends on delivering the build on time and budget.

Latest Financial and Operational Performance

KEFI's FY2025 results, published 8 June, showed the company still pre-revenue: a loss for the year of £9.694 million, against a £1.206 million profit in 2024, reflecting ramped-up activity around the financing. Cash at 31 December 2025 stood at £8.772 million, up sharply from £185,000 a year earlier, after £16.607 million net was raised from share issuances. A further £35.6 million raised in April 2026 has topped up the Balance Sheet ahead of drawdown.

In Saudi Arabia, KEFI's interest in joint-venture vehicle GMCO was diluted to roughly 13% (from 15.34%) after an October 2025 capital increase, as partners funded work at Hawiah and Jibal Qutman. A final Investment decision on Jibal Qutman Stage 1, an oxide open pit, is targeted for the second half of 2026, with Hawiah Stage 1 likely to follow.

Key Numbers

  • Tulu Kapi development budget: c.$340m ($240m senior debt, $20m Ethiopian government equity, $30m KEFI equity, $20m Chancery royalty, ~$60m fleet services)
  • Commissioning targeted late 2027; full production mid-2028
  • Mine plan: c.1.215m oz gold from 17m tonnes at 2.4g/t
  • AISC estimate: $1,004—$1,144/oz; post-debt breakeven c.$1,400/oz
  • FY2025 loss: £9.694m (2024: £1.206m profit); year-end cash: £8.772m
  • 2025 net share issuance proceeds: £16.607m; further £35.6m raised April 2026
  • KEFI's stake in Saudi joint venture GMCO: diluted to c.13%
  • Share price c.1.26p; market cap c.£174m (7 August 2026)

Growth Opportunities

Beyond first gold at Tulu Kapi, KEFI's stated strategy is a broader production base from its Saudi Arabian portfolio. GMCO's resource base includes around 0.9 million ounces of gold and silver at Jibal Qutman and roughly 2.6 million gold-equivalent ounces at Hawiah, which KEFI describes as among the richer volcanogenic massive sulphide deposits globally by grade. It intends to develop these through joint-venture and self-funded structures rather than further parent-level dilution, aiming eventually to exceed Tulu Kapi's output group-wide. It has also flagged a Partnership involving miner Hancock Prospecting, a new exploration licence at Umm Hijlan, and plans to move its listing to the LSE Main Market, targeting 2028.

Risks Investors Should Know

Construction risk is now central: cost overruns, contractor delays or equipment shortfalls could push commissioning beyond late 2027. Economics are gold-price sensitive too — the wide modelled NPV range reflects assumptions between $3,000 and $5,000 per ounce, and a sustained price pullback would compress returns and cash available to service the debt. Ethiopia carries country risk, including currency convertibility and the still-incomplete Phase 2 resettlement. KEFI's Saudi interest has already been diluted by capital increases it did not fully fund, and further dilution remains possible. KEFI also has a long history of raising equity to bridge funding gaps.

What to Watch Next

The clearest catalyst is drawdown of the $240 million debt facility, guided for the fourth quarter — confirming lenders are satisfied construction is on track. Investors should also watch Phase 2 resettlement progress, further contractor updates, and any Jibal Qutman Stage 1 investment decision, expected in the second half. Interim results, likely in September, should give the first full financial picture since April's fundraising and construction start.

Outlook

KEFI's August update confirms what the market has waited years to hear: Tulu Kapi is finally being built, funded and on the timetable the company has set out. The financing package, groundbreaking ceremony and contractor mobilisation are real, verifiable progress after a long history of delay. But the distance to a producing, cash-generative mine remains considerable, running through 2027 into 2028, and investors weighing the modelled valuation upside against execution and country risk should treat the coming debt drawdown and September's interim results as the next genuine tests of whether this build stays on track.