Key Highlights
- KEFI has closed a roughly US$340m Tulu Kapi financing package, with a final US$20m equity-ranking Royalty via Chancery Royalty; about US$30m remains to be finalised.
- Construction is under way, with contractors mobilised, resettlement Phase 1 substantially complete and over half of major plant equipment ordered.
- Commissioning is targeted for late 2027 and full production for mid-2028; the final Debt drawdown is a Q4 2026 event.
- AISC is guided at about US$1,004–1,144/oz with a post-debt break-even near US$1,400/oz; KEFI expects to retain about 83% of the project.
- KEFI holds about 13% of Saudi JV GMCO (Hawiah copper-gold, Jibal Qutman gold), with a Jibal Qutman FID targeted for H2 2026.
KEFI (LSE:KEFI) Gold and Copper has spent the best part of a decade trying to move its Tulu Kapi gold project in western Ethiopia from feasibility to fact. Financing, security and government-agreement hurdles repeatedly pushed back the timetable, testing the patience of long-suffering shareholders. In 2026 the picture has changed materially: the funding package is largely in place and construction has begun.
The company has closed a project-financing package of roughly US$340 million and mobilised its principal contractors to site, marking the transition from planning to build. With gold prices at historically strong levels, the Economics of Tulu Kapi look more compelling than at any point in the project's long gestation — though first gold is still targeted for 2028, and a portion of the financing remains to be finalised.
Latest Development
An operational update in early August 2026 confirmed that development remains on schedule, with commissioning targeted for late 2027 and full production in mid-2028. Physical progress includes resettlement housing, an electrical substation and a new access road from the highway to site. Phase 1 of the Resettlement Action Plan is substantially complete, with all compensation agreements finalised and around 90% of payments distributed, and Phase 2 preparation under way over the Mining and processing areas.
On procurement, KEFI said more than half of the major plant equipment — including the SAG mill, crushers, cyclones and processing components — has been ordered or is ready to order, while principal contractors Lycopodium, EEP, ERA and BCM mobilise personnel and subcontractors.
The Numbers
The financing package totals about US$340 million, and its final piece was a US$20 million equity-ranking royalty arranged with Chancery Royalty Limited, structured to be paid alongside Shareholder distributions. A further roughly US$30 million was reported as pending finalisation, comprising development costs to be settled in KEFI shares and additional royalty funding — so investors should note the funding is largely, but not entirely, closed, and full debt drawdown is a Q4 2026 event.
On project economics, KEFI has pointed to an All-In Sustaining Cost in the region of US$1,004–US$1,144 per ounce and a post-debt break-even of roughly US$1,400 per ounce, well below prevailing gold prices.
The Investment Story
Tulu Kapi is a conventional open-pit gold project with a subsequent underground phase, offering relatively low costs and strong Leverage to the gold price. For KEFI, delivering it would transform the company from a perennial developer into a cash-generating producer, with production targeted from 2028. The long delay means much of the permitting, government-agreement and resettlement groundwork is now done, arguably de-risking the remaining path relative to earlier years.
KEFI also carries a Saudi Arabian growth arm through its roughly 13% interest in Gold & Minerals Company (GMCO), the joint venture that holds the Hawiah copper-gold volcanogenic massive sulphide deposit and the Jibal Qutman gold project, and which counts Hancock Prospecting and Ajlan & Bros among its partners. A final investment decision on Jibal Qutman is targeted for the second half of 2026.
What Could Drive the Shares?
Execution milestones are the obvious catalysts: completing the final debt drawdown in Q4 2026, hitting construction and commissioning targets through 2027, and ultimately pouring first gold in 2028. Each de-risking step that keeps the project on schedule and budget could support a re-rating, particularly given the leverage a producing mine would bring at current gold prices.
In Saudi Arabia, a final investment decision on Jibal Qutman and progress at Hawiah could crystallise value in the GMCO stake. A sustained strong gold price would materially enhance Tulu Kapi's economics and cash generation, while any reduction in the remaining financing overhang would reduce dilution risk.
Risks Investors Should Watch
Construction and ramp-up risk are front and centre: building a mine on schedule and budget in a frontier setting is demanding, and cost overruns or delays would strain a company that has only recently secured funding.
Ethiopia carries jurisdiction risk, including security, currency and political considerations that have historically slowed the project. Gold-price Volatility cuts both ways, and the Saudi exposure is held via a minority stake, limiting direct control. Investors should remember Tulu Kapi is a project under construction, not yet a producing mine.
What Happens Next?
The key near-term markers are the Q4 2026 debt drawdown trigger and the finalisation of the remaining funding, followed by continued construction progress towards commissioning in late 2027 and full production in mid-2028. Updates on resettlement Phase 2, equipment delivery and contractor mobilisation will indicate whether the schedule is holding.
In Saudi Arabia, watch for the targeted final investment decision on Jibal Qutman in the second half of 2026 and any development steps at Hawiah. Regular operational updates and the gold price will shape sentiment as the build advances.
Bottom Line
KEFI (LSE:KEFI) Gold and Copper has finally moved Tulu Kapi from a financing question into a construction reality, with contractors on site, resettlement largely complete and a roughly US$340 million package substantially closed. The bull case is a low-cost gold project being built into a strong gold market, with Saudi optionality on top. The risks are construction and ramp-up execution, a not-yet-fully-closed funding package, and Ethiopian jurisdiction risk. The central debate is whether KEFI can deliver first gold on time and budget in 2028 and convert years of groundwork into cash flow.