Metals Exploration (LSE:MTL) has fully drawn its US$27.0 million equipment Loan and says first gold at its La India project in Nicaragua remains on track for December 2026. Maiden drilling at the nearby La Grecia prospect returned a best intercept of 1.30 metres at 36.5 g/t gold.

Financing fully drawn ahead of first gold

AIM-quoted Metals Exploration Plc (LSE:MTL), which has gold production, development and exploration operations in the Philippines and Nicaragua, said on 28 September 2026 that it drew the final US$6.8 million of its US$27.0 million equipment loan on 23 September 2026. The facility, provided by financing partner Banco de America Central S.A. (BAC), is now fully drawn.

Following the final drawdown, the company reported cash of £25.8 million, which it put at approximately US$34.5 million using an Exchange Rate of £1:US$1.33.

The loan has a five-year term, maturing on 17 August 2031. It carries a Variable Interest Rate of six-month Term SOFR plus a Margin of 3.15%, with an initial rate of 7.00% a year and a floor of 6.85%. Repayment terms include a 12-month grace period during which only interest is paid, followed by 48 equal monthly instalments.

The company describes its Runruno asset in the Philippines as providing ongoing cash flow.

La India construction progress

The company said first gold production at La India remains on track for December 2026 and set out progress across the process plant. Ring fit-out of the carbon-in-leach (CIL) tanks is complete, with top-structure assembly and grating installation under way, and the oxygen plant has been installed.

All process plant conveyors have been installed and the pebble-crushing conveyor is structurally complete. Structural steel for the grinding building has been completed. The head ends, trunnions and middle shell of the SAG mill have been lifted into their final positions, and preparation of the ball mill's girth gear is under way. Thickener tank assembly is ongoing, with the leach thickener weirs complete. Lining of the tailings storage Facility has commenced, the run-of-mine bin is on site and electrical cable tray installation has begun.

Chief Executive Darren Bowden said: "Construction at La India continues to advance at pace across the process plant. CIL tank ring fit-out is now complete, the SAG mill's key components have been lifted into position, and the ball mill's girth gear is being prepared for installation."

The announcement did not update production guidance, Capital cost estimates or resource figures for La India.

Maiden drilling at La Grecia

At La Grecia, around 50 kilometres north-west of La India, the company has completed a maiden scout drilling campaign of 2,450 metres. The prospect was previously explored by Newcrest, which the company said collected 80 rock chip samples averaging 18.84 g/t gold.

Hole LGDD-004 returned 1.30 metres at 36.5 g/t gold and 165.78 g/t silver from 155.4 metres, including 0.7 metres at 67.4 g/t gold and more than 300 g/t silver from 156.0 metres. The same hole intersected a second vein of 1.90 metres at 6.03 g/t gold and 106.65 g/t silver from 164.7 metres, including 0.5 metres at 20.7 g/t gold. A third vein structure encountered between 158.9 and 160.1 metres appears to have been previously mined, and no sample was recovered. Hole LGDD-001 returned 0.65 metres at 3.96 g/t gold and 12.6 g/t silver from 120.85 metres.

The reported widths are downhole intervals; the announcement does not state true widths. The results have not been incorporated into any resource estimate.

Mr Bowden said the initial campaign "has returned early but promising results, and we look forward to refining our geological model."

Next steps

Assay results for the remaining La Grecia holes are expected in October 2026. A surface sampling and mapping programme has been initiated, and follow-up drilling is planned for the first quarter of 2027. At La India, the target remains first gold in December 2026.