HyProMag USA, the rare earth magnet recycling venture in which Mkango has an indirect interest, has secured power from Oncor for its planned Texas Hub. The project is targeting commissioning of cutting and finishing operations in the first half of 2027 and completion of Phase 1 by mid-2028.
What was announced
Mkango Magnetic Materials Limited (LSE:MKA), which is quoted on AIM and the TSX Venture Exchange, said on 13 October 2026 that HyProMag USA LLC had secured power capacity from Oncor Electric Delivery Company LLC for its Texas Hub, a rare earth magnet recycling and manufacturing project in Texas.
The announcement said power has been secured for both the initial cutting and finishing operations and for Phase 1. Power for Phase 2 is to be supplied through a sub-station upgrade, for which no date was given. The amount of capacity secured, in megawatts, was not disclosed. The company said electricity is expected to come predominantly from renewable sources.
HyProMag USA is owned 50:50 by CoTec Holdings Corp. and HyProMag Limited. HyProMag Limited is wholly owned by Maginito Limited, which in turn is owned 79.4% by Mkango and 20.6% by CoTec. On our calculation, that gives Mkango an indirect economic interest of about 39.7% in HyProMag USA.
The project plan
The first stage is a cutting and finishing facility, targeted for commissioning in the first half of 2027. It will process neodymium-iron-boron (NdFeB) magnet blocks, initially supplied from HyProMag Group operations, into finished magnets. The facility is designed to support qualification to the ASTM A977/A977M standard, with quality systems aligned to ISO 9001, and is also intended to serve as a training facility ahead of the main Texas Hub developments.
Phase 1 completion is targeted for mid-2028. It is planned to produce about 550 tonnes per annum (tpa) of sintered NdFeB magnet blocks and finished magnets, plus about 484tpa of co-products, giving total payable production of about 1,034tpa. Phase 2 is planned to produce about 1,048tpa of NdFeB magnet blocks and cylinders and about 478tpa of co-products, for total payable production of about 1,526tpa. No target date was given for Phase 2. On our calculation, Phase 2 output would be about 492tpa, or roughly 48%, higher than Phase 1 on a total payable basis.
The announcement does not disclose capital expenditure or the funding arrangements for HyProMag USA, and no customer offtake agreements were announced.
Contractors and comment
Pegasus TSI and BBA USA are providing engineering and EPCM services, and Pegasus has started a request-for-quotation process to select a general contractor for the cutting and finishing operations. Weston Solutions is handling permitting.
Julian Treger, chief executive of CoTec, said that securing power with Oncor and advancing permitting through Weston Solutions "further de-risk the project" and show "continued progress towards establishing a domestic and sustainable rare earth magnet supply chain in the United States".
Management expects the 2027 cutting and finishing operations to establish US magnet finishing and qualification capabilities, with Phase 1 adding integrated recycling and magnet manufacturing capacity. These are company targets.
Separately, the announcement refers to Mkango's Songwe Hill project, which has received US$4.6m in reimbursable front-end engineering and design (FEED) funding from the US International Development Finance Corporation.
What to watch next
The company's forward-looking statements flag a range of risks, including financing, permitting, contractor performance, the timing of the Oncor sub-station upgrade, customer qualification and securing commercial offtake. Points to watch include the appointment of a general contractor, progress on permits, any funding announcements and whether the first-half 2027 commissioning target is met.
SP Angel Corporate Finance is Mkango's nominated adviser and joint broker, alongside joint brokers Cavendish Capital Markets and H&P Advisory.