Pensana Plc (LSE:PRE) now expects construction of its Longonjo rare earths project to complete in late 2028, having slowed some activities while financing is finalised. The company has also accepted a farm-in offer from ASX-listed Tyranna Resources for its nearby Coola project.
What was announced
On 25 September 2026, Pensana Plc published an update covering the financing of its Longonjo mine development and a farm-out of its Coola exploration project.
The company said construction at Longonjo is over 30% complete. The overall construction schedule is now expected to be extended from the previously announced 2028 to late 2028.
Separately, Pensana has accepted an exploration farm-in offer from Tyranna Resources for Coola, under which US$2.6 million will be spent over three years with a view to diluting Pensana's interest in the project to 20%.
Why the Longonjo timetable has moved
Pensana attributed the revised schedule to a deliberate reduction in activity while financing discussions continue. According to the announcement, "outstanding detailed construction design activities, high-cost site activities and long term procurement items have been ramped down until the financing has been finalised."
The announcement therefore links the timing of completion to the conclusion of the funding package. It does not set out a specific date by which Pensana expects financing to be finalised, nor does it quantify any change to the project's Capital cost as a result of the slower pace of work.
The funding picture
The Longonjo financing includes an Investment of US$165 million from Cascade, which is backed by the State of Qatar. Pensana said it has received US$15 million of that amount to date. On the figures given, this leaves US$150 million of the Cascade investment still to be received (calculation based on the disclosed amounts). The announcement does not disclose the instrument type, the conditions attached to further payments or the timing of subsequent tranches.
Pensana also plans Debt facilities through ABSA and EXIM banks. The size and terms of these facilities were not disclosed. The company said it has entered into detailed financing discussions and has had successful detailed negotiations with potential major offtake partners, and indicated that support for the financing is contingent on offtake agreements with major partners. The offtake counterparties were not named, and no signed offtake agreements were announced.
Pensana describes Longonjo as one of the world's largest undeveloped rare earth mines. The company's stated target is initial production of 20,000 tonnes per annum of magnet rare earth carbonate (MREC), with potential expansion to 40,000 tonnes per annum. These are company targets and depend on the project being financed and completed.
The Coola farm-out
Coola lies about 30km from Longonjo. Under the farm-in, Tyranna is to fund US$2.6 million of exploration over three years. If that expenditure is completed, Pensana's interest would be diluted to 20%, meaning Tyranna would hold the balance of 80% (calculation, assuming no other parties hold interests; the announcement does not state Tyranna's resulting stake explicitly).
The announcement does not give details of the exploration programme, any staged earn-in milestones or the licence terms. Pensana (LSE:PRE) noted that, should a mine be successfully developed at Coola, the option remains for its product to be treated at Longonjo.
What to watch next
Key items for investors are the finalisation of the Longonjo financing, including the ABSA and EXIM debt facilities, receipt of the remaining Cascade funds, and the signing of offtake agreements on which that support depends. Any update on whether the late 2028 schedule holds once activities are ramped back up will also be relevant, as will Tyranna's progress at Coola.
The announcement did not include comment from Chairman Paul Atherley, Chief Executive Tim George or Chief Financial Officer Rob Kaplan.