Highlights

• Premier African Minerals has begun start-up activities at the Zulu Lithium and Tantalum Project this month.

• Crushing operations are underway as an early step in the company's restart campaign at Zulu.

• Water now circulates through the mica circuit to establish the plant's operating water balance before ore arrives.

• The company is targeting first ore feed to the processing circuit during the week of the update.

On the ground at Zulu, the crushers are turning again. Premier African Minerals (LSE:PREM) has set out an operational update showing start-up activities under way at its Zulu Lithium and Tantalum Project, with water moving through the plant and ore feed lined up as the next step. The update, dated 17 November 2026, describes a restart moving through its early, sequential stages.

Start-Up Activities Begin

The restart follows a provisional agreement reached with staff, which enabled Premier African Minerals (LSE:PREM) to commence start-up activities at the project. Work has since moved into the physical start-up sequence.

Crushing is now underway. In a processing restart, crushing prepares the feed that will later pass into the Downstream circuit, so its resumption is an early marker of the plant moving back towards operation.

Water Balance in the Mica Circuit

Alongside crushing, the company has started circulating water through the mica circuit. The purpose of this step is to establish the operating water balance of the circuit before it receives ore.

With crushing and water circulation running side by side, the plant is being readied on two fronts ahead of the introduction of ore.

Ore Feed Targeted This Week

Ore has not yet been fed into the processing circuit. Premier African Minerals is targeting the start of ore feed within the week of the announcement, which would mark the move from preparatory activity to processing.

Premier African Minerals (LSE:PREM) has said it will provide further updates as the restart campaign progresses. The update does not include production, throughput or recovery figures, so those details are expected to follow in later reports as the campaign advances.

The Restart Sequence at a Glance

• Start-up activities commenced at the project

• Crushing underway

• Water circulation through the mica circuit started

• Ore feed to the processing circuit targeted for the week of the update

• Further updates to follow as the campaign continues

What a Restart Sequence Involves

Restarting a processing plant is carried out in stages, and the update describes the early ones. Crushing reduces the size of the ore so that it can pass through the downstream circuit. Water circulation in the mica circuit establishes the operating water balance, which is the amount of water entering, circulating and leaving the circuit, before ore is introduced. With both under way, the plant is being readied on two fronts ahead of ore feed, which is targeted for the week of the announcement.

The Project and the Staff Agreement

The Zulu Lithium and Tantalum Project produces materials that are used in batteries and electronics, and the restart follows a provisional agreement with staff that enabled start-up activities to commence. The update does not give details of the terms of that agreement, so the key facts are that the agreement was reached, that start-up activities began and that crushing and water circulation are running. Ore has not yet been fed into the processing circuit, and the company says it will provide further updates as the restart campaign progresses. The update does not include production, throughput or recovery figures, which means those details will be reported in later announcements once the plant is operating with ore. A restart campaign is normally monitored through a series of operating indicators, such as the rate at which ore is processed and the proportion of valuable minerals recovered, and the company has indicated that information of that kind is expected to follow. For readers following Premier African Minerals, the sequence is clear: provisional agreement, start-up activities, crushing, water circulation and then ore feed. Each step marks progress towards a plant operating under normal conditions. The update is dated 17 November 2026 and provides a point-in-time description of where the campaign stands.