Key Highlights

  • The Barroso Definitive Feasibility Study confirms a post-tax NPV of $913 million and 43.2% IRR, with first production targeted for 2028.
  • A maiden JORC Probable Reserve of 20.0 million tonnes at 0.99% Li2O underpins a 14-year mine life.
  • Savannah secured a €110 million non-reimbursable grant from the Portuguese State in January 2026 to help fund construction.
  • Barroso was designated a “Strategic Project” under the EU's Critical Raw Materials Act, reflecting its role in reducing European reliance on Chinese lithium Supply .
  • Legal challenges, including a case at the European Court of Justice and local land-access disputes, remain unresolved.

LSE-listed Savannah Resources has completed the Definitive Feasibility Study for its Barroso lithium project in Portugal, confirming robust Economics and a 2028 production target. Legal challenges and community opposition remain unresolved.

Savannah Resources (LSE:SAV), the LSE-listed developer behind Europe's largest known spodumene lithium deposit, has passed one of the biggest tests in its near-decade-long history. On 15 July 2026 the company published the Definitive Feasibility Study (DFS) for its Barroso project in northern Portugal, setting out detailed economics for a mine designed to supply battery-grade lithium concentrate to Europe's electric-vehicle industry. For a company that has spent years navigating permitting delays, community opposition and volatile lithium prices, the DFS marks a tangible step from paper project to construction-ready asset.

What Happened

The DFS confirmed a first maiden JORC Probable Reserve of 20.0 million tonnes at 0.99% Li2O, drawn from a wider Mineral Resource of 39.1 million tonnes at 1.05% Li2O that was upgraded earlier in the year following a 12,463-metre Phase 2 drilling campaign. The study outlines a conventional open-pit, excavator-truck operation across the Pinheiro, Grandão, NOA, Reservatório and Aldeia pits, feeding a processing plant using crushing, dense-media separation, grinding, magnetic separation and flotation to produce spodumene concentrate at a target grade of 5.5% Li2O.

The study followed a January 2026 announcement that Savannah had secured a €110 million non-reimbursable grant from the Portuguese State, split between roughly €82.25 million for initial Capital Expenditure and €27.42 million tied to operational milestones, awarded under Portugal's Investments in Strategic Sectors Incentive Scheme. Together, the DFS and grant give the company a clearer route toward a construction decision, with first production still targeted for 2028.

Why It Matters

Barroso is more than another junior Mining story. The European Commission designated it a "Strategic Project" under the Critical Raw Materials Act in March 2025, reflecting Brussels' push to reduce reliance on Chinese-controlled lithium supply chains. Europe currently imports the vast majority of the lithium feedstock used in its nascent battery-manufacturing base, and Barroso is positioned as a rare domestic alternative. The DFS numbers matter because they move the project from a resource story to an investable, de-risked case with defined capital and operating costs, a mine plan, and a state-backed funding package attached to a specific timeline.

Latest Financial and Operational Performance

Savannah remains a pre-revenue developer, and its financial statements reflect that. For the year to 31 December 2025, the company reported a loss from continuing operations of £4.0 million, an improvement on the £4.4 million loss in 2024, with administrative costs broadly flat at £4.4 million. It ended the year with £17.2 million in bank funds plus £5.0 million in longer-term deposits, having raised £14.6 million gross through two placings during the year. Intangible assets, largely capitalised DFS and licensing spend, rose 42% to £30.8 million. As of early August 2026, shares traded around 5.7p, valuing the company at roughly £146.8 million, within a 52-week range of 3.30p to 7.70p.

Key Numbers

  • DFS post-tax NPV8: US$913 million; post-tax IRR: 43.2%
  • Initial capex: US$417 million gross, US$283 million net of the Portuguese grant
  • Average C1 operating cost: US$473/tonne concentrate; AISC: US$646/tonne
  • Payback period: 1.9 years; mine life: 14 years
  • Life-of-mine spodumene concentrate output: 2.56 million tonnes (183,000 tonnes/year at steady state)
  • Life-of-mine EBITDA: US$3.2 billion; free Cash Flow : US$1.9 billion
  • JORC Reserve: 20.0Mt at 0.99% Li2O; JORC Resource: 39.1Mt at 1.05% Li2O
  • FY2025 cash and deposits: £22.2 million (£17.2m banked plus £5.0m long-term deposits); FY2025 loss: £4.0 million
  • €110 million Portuguese State grant secured January 2026

Growth Opportunities

The DFS itself flags upside beyond the base case. Management has pointed to an exploration target of 35–62 million tonnes at grades of 0.9–1.2% Li2O beyond the current reserve, suggesting scope to extend mine life or expand throughput once Phase 1 is established. The project's "Strategic Project" status also opens access to EU funding mechanisms and streamlined permitting not available to non-designated developments, while the grant's capex-weighted structure should reduce the funding gap to reach a final Investment decision, expected by end-2026. With European automakers and battery makers under pressure to secure non-Chinese lithium supply, Barroso's EU location is itself a commercial selling point that could support offtake discussions as construction financing is arranged.

Risks Investors Should Know

Barroso has faced sustained opposition for close to a decade, and that has not abated. In February 2026, environmental law group ClientEarth and the local campaign group União de Defesa de Covas do Barroso filed a case at the European Court of Justice challenging the Commission's strategic-project designation, citing risks to protected species, water resources, mining-waste storage safety and traditional agropastoral farming in a region recognised by the UN's Food and Agriculture Organization for its heritage land-management practices. Separately, a local baldios (commons) association sought a court injunction in June 2026 against a temporary land easement granted to Savannah; Portugal's government overrode the suspension, allowing fieldwork to resume, but the underlying legal dispute continues. Beyond permitting risk, investors should weigh Savannah's continued reliance on further capital raises before construction funding is secured, lithium price Volatility that could pressure DFS economics, and the execution risk inherent in any first-time mine build, including the pending Environmental Licence and RECAPE submission.

What to Watch Next

Near-term catalysts include formalisation of the Portuguese grant with AICEP, progress on the Environmental Licence following the 2023 positive Environmental Impact Statement, and the RECAPE submission targeted around the DFS release. Investors should also track the pending European Court of Justice case, further land-access disputes in Covas do Barroso, progress toward a final investment decision expected by end-2026, and any offtake or partner announcements that would de-risk the roughly US$283 million net capital requirement.

Outlook

The Barroso DFS gives Savannah Resources a credible, numbers-based case for Europe's largest known spodumene deposit, backed by meaningful state financial support and EU strategic status. But the project's economics cannot be separated from its politics: legal challenges at both EU and local level, and entrenched community resistance in Covas do Barroso, remain unresolved and could yet affect timelines. For investors, Barroso is a project where the technical and financial derisking has advanced markedly in 2026, while the social licence to operate remains the swing Factor to watch.