Serabi Gold PLC (LSE:SRB) spent a decade as a modest producer of 30,000 to 40,000 ounces a year from Brazil's Tapajós region. That description is now out of date. Record output of 44,169 ounces in 2025, a realised gold price approaching $5,000 an ounce in early 2026, a debt-free Balance Sheet holding $65.7m of cash and a maiden Dividend have reshaped the Investment case.

The question for the rest of 2026 is whether the next leg of growth arrives on schedule. Serabi is guiding to more than 53,000 ounces this year, is installing a fourth ball mill and is waiting on a permanent licence for its Coringa mine. The departure of finance chief Colm Howlin, announced on 1 September 2026, adds a management transition to that list.

CFO steps down after 13 years as Q2 output edges higher

On 1 September 2026 Serabi confirmed that Colm Howlin had stepped down as chief financial officer and director with effect from 28 August 2026 after 13 years with the company. No reason was given. Nick Box, formerly of Harbour Energy and previously CFO of AIM-quoted SDX Energy, has been appointed interim CFO but will not join the board. Chairman Michael Lynch-Bell said the board "conveys its thanks to Colm for his 13 years of service to Serabi".

The change follows the second-quarter update of 23 July 2026. Serabi produced 11,007 ounces in the three months to 30 June 2026, 5% more than a year earlier, taking first-half output to 23,049 ounces against 20,545 ounces. Milled grade slipped to 6.21 g/t from 7.05 g/t in the first quarter.

Cash rose to $65.7m at 30 June 2026 from $64.4m at the end of March. Chief executive Mike Hodgson described "a solid second quarter", adding that "Serabi remains in a strong cash position with zero Debt and multiple organic growth catalysts expected later this year". Guidance for production exceeding 53,000 ounces in 2026 was reiterated, although it assumes Coringa's permanent licence is granted by the fourth quarter.

A Brazilian underground gold producer with two mines

Serabi is a gold exploration, development and production company operating in the Tapajós region of Pará state, northern Brazil. Its shares trade on AIM, on the Toronto Stock Exchange as SBI and on the OTCQX. Revenue comes almost entirely from selling gold, so Earnings are highly geared to the metal price and to the dollar-real exchange rate.

The Palito Complex has produced continuously for more than ten years and hosts the group's processing plant. Coringa, the second mine, is ramping up across its Serra and Meio zones; its ore passes through an ore sorter before milling at Palito. A fourth ball mill, due to be operational by the fourth quarter of 2026, should lift throughput from around 650 to about 900 tonnes a day.

The estimate published on 28 April 2026, effective 31 January 2026, put measured and indicated resources at 730,800 ounces at 9.1 g/t, up 29% on March 2025, and inferred resources at 653,300 ounces, up 50%. Palito proven and Probable Reserves rose 55% to 228,400 ounces. Management's Phase II target is 1.5 to 2.0 million ounces.

Record 2025 results and a sharply stronger first quarter of 2026

Audited results for the year to 31 December 2025, published on 1 May 2026, showed revenue of $155.8m, up 65% on $94.5m in 2024, as production rose 18% and the realised gold price climbed 45% to $3,481 an ounce. EBITDA more than doubled to $77.9m, profit before tax rose 112% to $68.7m and profit after tax reached $53.9m, or 71.18 cents per share against 36.73 cents. All-In Sustaining Cost was $1,816 an ounce, 7% higher than in 2024, and year-end cash was $49.2m. The board declared an inaugural dividend of 5 pence per share, paid on 10 July 2026, and targets returning 20% to 30% of free Cash Flow through dividends or Buybacks in 2026.

The first quarter of 2026, reported on 29 May 2026, was stronger still. Revenue of $50.6m was 83% ahead of the first quarter of 2025 on gold sales of 10,323 ounces at an average realised price of $4,926 an ounce. EBITDA was $29.2m against $12.4m, profit before tax $27.4m against $10.8m and profit after tax $21.0m, or 27.72 cents per share. Serabi repaid its remaining $5.3m Banco Santander Loan in January and ended March with $64.4m of cash and no debt.

Unit costs are heading the other way. Cash cost per ounce rose 47% year on year to $1,863 and all-in sustaining cost 40% to $2,293, partly reflecting the inclusion of Meio zone costs after commercial production began there. Financial statements for the six months to 30 June 2026 had not appeared on the Investegate RNS feed as of 2 September 2026.

What could drive the stock next?

The most important milestone is the permanent installation licence for Coringa, which operates under a temporary permit expiring in January 2027. The FUNAI indigenous impact study was approved in March 2026; the remaining step is federal INCRA approval of land-use change, after which the state agency SEMAS can issue the licence. Approval would remove a regulatory overhang and underpin the 53,000-ounce guidance.

Commissioning of the fourth ball mill, completion of the move to mechanised sublevel stoping at Coringa and further drilling at the Serra South discovery are the other near-term catalysts, alongside first-half results. The company's website sets out a longer-term ambition of 100,000 to 200,000 ounces a year within three to five years.

Risks investors should watch

Licensing is the most visible risk. If the Coringa permit is delayed beyond the expiry of the temporary permit, production guidance and the growth plan would both be affected, and a compensation agreement with the indigenous community is still being negotiated.

Cost Inflation is the second. A 40% rise in all-in sustaining cost in the first quarter of 2026 was masked by a much higher gold price; a meaningful fall in the price would expose that cost base, and a stronger real would compound it. Palito's 2026 feed grades have so far run below last year's levels.

The exit of a 13-year CFO ahead of the half-year results, with an interim replacement who is not on the board, creates a period of transition in the finance function. Serabi is also a small, single-country producer exposed to Brazilian regulation, and its growth plan depends on converting resources into reserves at Coringa, which has no declared reserve at present.

Outlook

Serabi enters the final third of 2026 with a strong balance sheet, record earnings momentum and a clear list of deliverables. Whether the gold story is just getting started rests on the Coringa licence arriving, the fourth ball mill starting on time and first-half results showing that higher revenues are converting into cash despite rising unit costs. With gold having done much of the heavy lifting so far, execution on the ground will decide the next chapter.