Tertiary Minerals (LSE:TYM) is preparing to start its first diamond drilling at Target A1 on the Mushima North project in Zambia, aiming to test mineralisation to around 200m vertical depth beneath its silver-copper-zinc Exploration Target.
What was announced
Tertiary Minerals plc, the AIM-quoted explorer, said on 29 October 2026 that mobilisation had begun for a diamond drill programme at Target A1 on its Mushima North project in Zambia, held under licence 27068-HQ-LEL. It will be the company's first diamond drilling on the project.
The programme is planned at about 1,000m, made up of up to four holes of 200m to 250m each, inclined at roughly -60 to -70 degrees. Drilling is expected to start early the following week and take about four weeks.
The holes are designed to test to about 200m vertical depth. By comparison, the current Exploration Target extends to about 95m and the deepest Phase 4 drilling reached 125m vertical depth. The company said the aims are to test for deeper mineralisation and possible underlying primary sulphides, to improve geological understanding, and to provide drill core for metallurgical testwork.
The numbers
Target A1's Exploration Target, previously reported on 30 March 2026, is 15 to 30 million tonnes at 40 to 60 g/t silver equivalent, or up to 58 million ounces of silver equivalent. An Exploration Target is conceptual and is not a Mineral Resource.
The Discovery Zone is described as a near-surface tabular body in the oxide zone, about 500m long, 300m wide and up to 75m thick at a 25 g/t silver equivalent cut-off. It remains open to the northwest, southwest and at depth. Phase 4 drilling defined a higher-grade zone of up to 400m by 150m at surface, extending to 125m vertical depth. Associated elements include bismuth up to 0.53%, antimony up to 0.22%, cobalt at 0.39% and gallium up to 40 g/t.
More than 3,600m of reverse circulation drilling has already been completed to support a Mineral Resource Estimate. Phase 4 scout drilling also identified a new shallow copper zone, the Western Zone, about 900m west-southwest of the Discovery Zone, which remains open.
Core from the new programme will be analysed on site by portable XRF for copper and zinc, with external laboratory assays for silver, copper, zinc, cobalt, bismuth, antimony, gallium, germanium and rare earths. Laboratory results are expected about six to eight weeks after each batch is submitted. The cost of the programme was not disclosed.
Background
Target A1 lies 28km east of the Kalengwa copper-silver mine, which is being redeveloped and was historically high grade at about 11% copper. Tertiary has a non-binding technical cooperation agreement with First Quantum Minerals, announced on 15 September 2022.
The licence is held through Copernicus Minerals Limited, which is owned 90% by Tertiary Minerals (Zambia) Ltd and 10% by Mwashia Resources Ltd. Other untested targets on the project, named B1, B2, B3 and C2, mostly lie within 12km of Target A1.
Managing director Richard Belcher, who is also the Competent Person for the announcement, said he looked forward to providing further updates "in the coming weeks".
What to watch next
Several near-term items were flagged. Final Phase 4 assays and initial metallurgical testwork results are described as expected imminently, and the company plans to publish a Mineral Resource Estimate before the end of the year. The diamond holes themselves should take about four weeks to complete, with laboratory results following six to eight weeks after each batch is sent.
The deeper drilling will be closely tied to the question of whether primary sulphide mineralisation sits beneath the oxide body. The announcement does not say whether diamond drilling results will be included in the planned resource estimate, and given the stated laboratory turnaround it is unclear whether they would be available in time.