Total Graphite (LSE:TGR) said initial bench-scale tests on graphite from its Madagascan operations achieved 99.2% fixed carbon purity without the use of hydrofluoric acid. The company is now optimising the process towards a 99.5% target as it works towards an Investment decision on a first Downstream plant.

First results from the downstream programme

Total Graphite plc (LSE:TGR), which describes itself as a specialist graphite and graphene producer in Madagascar and India, announced on 28 September 2026 that its first high-purity graphite (HPG) tests had produced material grading 99.2% fixed carbon (FC). The feedstock was graphite concentrate from its Vatomina operation in Madagascar.

The work was carried out at bench scale with two specialist institutes focused on advanced materials. The institutes were not named in the announcement. The company said the processing route uses mild reagents and avoids hydrofluoric acid (HF), a chemical widely used in conventional graphite purification, which it presented as a more environmentally conscious approach.

Optimisation work is now under way with the aim of reaching 99.5% FC. According to the company, material at that purity can currently sell for up to around US$3,500 per tonne. The announcement did not disclose expected production volumes, processing costs, recoveries or Capital Expenditure for a downstream facility, and the results remain at the bench-scale stage.

Three product streams

The testing forms part of a downstream materials programme the company formally began in late July 2026. It is developing three higher-value product streams: high-purity graphite, expandable graphite (EG) and active anode material (AAM), the last of which is used in Lithium-Ion Battery anodes.

Total Graphite said the strategy is intended to evolve the Business from an Upstream producer of graphite concentrate into an integrated producer of higher-value graphite materials. It pointed to Demand from Western markets for secure and diversified Supply of graphite from outside traditional producing regions.

Feedstock is expected to come from Vatomina in Madagascar and, in future, from the company's development projects in Mozambique. The company published a feasibility study update on its Montepuez project in Mozambique on 9 September 2026.

Chairman Christian Dennis said the company was "very encouraged by this early stage success" and that the aim is to "position the Company to participate across a much larger proportion of the graphite value chain." He added that "significantly greater value is created through downstream processing."

Background to the programme

In a 10 September 2026 update on the downstream materials programme, Total Graphite said bench-scale testing using Vatomina samples had begun, with initial results targeted by the end of September. The latest announcement meets that stated timetable. The earlier update listed Madagascar, India and the United States as potential locations for a downstream plant under evaluation.

The same 10 September announcement disclosed the issue of 10,925,000 ordinary shares at 1 pence each to settle £109,250 owed to three suppliers, of which 9,125,000 shares are subject to a six-month lock-in. Following admission of those shares, the company's issued Share Capital was 779,331,787 ordinary shares.

The company has also reported drilling at Vatomina, releasing initial drilling results on 17 August 2026 and infill drilling results on 8 September 2026.

Timeline and conditions

Total Graphite is targeting completion of technical studies and engineering, and a Final Investment Decision (FID) on its first downstream plant, by the end of 2026 or early 2027. The company said that decision remains subject to further testing, Board approval, financing and regulatory approvals. Construction would follow only after successful test work and Board approval.

Next steps include optimising the process to achieve 99.5% FC and evaluating potential sites for the plant. Separately, Mining at Vatomina is scheduled to restart in January 2027.

No financing arrangements for a downstream plant were disclosed in the announcement.