Tungsten West (LSE:TUN) is an AIM-listed developer restarting the Hemerdon tungsten-tin mine near Plymouth, one of the largest tungsten resources outside China. After a temporary share suspension in 2024 tied to delayed accounts, the shares resumed trading and, on the last available data, changed hands around 38p for a Market Capitalisation of roughly £474m, up several-fold over the prior year. The company is pre-revenue, funding a phased restart toward full commissioning targeted for early 2027.
Latest developments
Financing and construction have dominated. In August 2025 Tungsten West received a letter of interest from the US Export-Import Bank for financing of up to US$95m, and in February 2026 it raised up to £43m in Equity at 18p a share to fund the feasibility study, repay a bridge and accelerate the restart. In May 2026 it secured a US$25m bridging Loan from an entity linked to a substantial Shareholder , while a larger US$85m Debt package was said to be in final documentation. Restart milestones followed a phased plan — a fines gravity circuit in the third quarter of 2026, a coarse circuit in the fourth, and full commissioning in early 2027 — with over 120 staff onboarded and Mining equipment operational.
The financing picture, though, remains unfinished. As of the latest available information, the US$85m debt package had not been confirmed as closed, and the company’s reliance on a shareholder bridge loan and repeated equity raises underlines how fragile the funding path has been. Tungsten prices, meanwhile, have surged past US$3,000 per metric tonne unit, transforming the Economics of a restart that looked marginal only a few years ago.
Financial performance
Tungsten West is pre-revenue, and the restart is expensive. Its half-year results to September 2025 showed a pre-tax loss widening to about £40m, with net finance costs of roughly £37m reflecting the cost of bridging debt and financing instruments during construction. Funding over the past year has come from the February 2026 equity raise, the May 2026 bridge loan and earlier convertible notes — a pattern of repeated, high-cost financing that dilutes shareholders and pressures the Balance Sheet until first concentrate is produced and the larger debt package refinances the bridge.
Industry outlook
The backdrop is extraordinary. Tungsten prices have more than tripled since early 2025, driven by China — which supplies over three-quarters of global output — tightening export licences and quotas, restricting sales to defence-linked buyers, and by surging Western defence and stockpiling Demand , including a large US critical-minerals initiative. The United States has no active commercial tungsten mine. Hemerdon is positioned as a potential cornerstone of UK and European tungsten Supply security, giving the restart a strategic dimension beyond its economics.
Bull case
The bull case is a strategic, non-Chinese tungsten source restarting into record prices. Tungsten’s surge has transformed Hemerdon’s economics, multiple financing avenues are in play — US export-credit interest, a shareholder bridge, a planned larger debt package and equity — and the geopolitics create structural, defence-driven demand. A phased restart de-risks execution, with commissioning milestones already under way rather than merely planned.
Bear case and risks
The bear case is financing fragility and execution history. Repeated recapitalisations, a widening loss and heavy finance costs show a balance sheet under strain, and the key US$85m debt package was not confirmed closed. Hemerdon’s troubled past — a previous operator collapsed after cost overruns — is a cautionary precedent for a capital- and staffing-intensive restart. Economics are fully leveraged to a tungsten price that, while high, is volatile, and reliance on equity and a related-party bridge implies further dilution and governance questions.
Key catalysts
Catalysts include confirmation of the larger debt package, commissioning of the fines and coarse gravity circuits through the second half of 2026, any progression of US Export-Import Bank financing, first concentrate production and Revenue , and full commissioning and ramp to nameplate capacity through 2027.
Conclusion
Tungsten West (LSE:TUN) sits at the intersection of a genuine strategic opportunity and a precarious balance sheet. Record tungsten prices and Western supply anxiety make Hemerdon more valuable than it has been in years, and commissioning is finally under way. But the revival is a race — between reaching first production and running out of financing headroom. Britain’s critical-minerals push gives the story its purpose; closing the funding gap is what will determine whether it succeeds.