Key Takeaways

  • Tungsten West (LSE:TUN) confirmed in July 2026 that it had started the phased restart of the Hemerdon mine, beginning with the fines gravity circuit and Downstream processing.
  • Full project commissioning is targeted for Q1 2027, with the coarse gravity circuit and the new-build crushing, screening and ore-sorting facilities sequenced across late 2026 and early 2027.
  • The restart is underpinned by a US$25m bridging loan, a mooted Debt Facility of up to US$85m, and a £22.3m equipment-finance package; cash stood at £25.5m at 31 March 2026.
  • Tungsten pricing quoted by the company is dramatically above the level assumed in the original feasibility study, a swing that reshapes the project's Economics if it holds.
  • Execution, funding completion and commodity-price sustainability remain the key variables between here and steady-state output.

Tungsten West plc is attempting one of the more closely watched restarts on London's junior market: the revival of the Hemerdon mine near Plymouth in Devon, one of the largest tungsten and tin resources outside China. The asset has a chequered history — it was previously operated by Wolf Minerals, which collapsed in 2018 — and Tungsten West has spent several years redesigning the process plant to lower operating costs and improve recoveries. The company has now moved from preparation into physical recommissioning, shifting the Investment case from "if" to "how well and how fast".

Latest Company Development

In its 8 July 2026 "Project Commissioning Update", Tungsten West said phased production ramp-up had commenced, beginning with the fines gravity circuit and downstream processing facilities. Chief executive Jeff Court described "rapid progress on the restart of Hemerdon with the first phase of recommissioning starting this month", framing it as "another significant milestone towards full project commissioning in Q1 2027".

The sequencing set out by the company runs as follows: the fines gravity circuit and downstream processing in the third quarter of 2026; the coarse gravity circuit in the fourth quarter; and the new-build crushing, screening and ore-sorting facilities completing into the first quarter of 2027, at which point full project commissioning is targeted. Management said the project was forecast to complete within budget. On the proposed headline, that guidance checks out: the restart has genuinely begun and full commissioning is targeted for early 2027 (Q1 2027), so the headline stands as written.

Staffing is being scaled in parallel: more than 100 employees had been recruited by the July update, against a target workforce of around 350 by early Q1 2027 — a proxy for how seriously the team is treating the timetable.

Financial and Operational Position

The restart is capital-intensive, and the funding picture has been assembled in stages. In its 21 May 2026 funding and debt update, Tungsten West detailed a short-term bridging Loan of US$25.0m from an entity controlled by substantial Shareholder Gregory Coffey, priced at SOFR plus 4.5% (around 8% per annum), unsecured, over a 366-day term. The company said a larger debt facility of up to US$85.0m had passed final Due Diligence with definitive documentation being finalised; that facility is intended in part to repay the bridge. A separate £22.3m mining-equipment finance package, arranged through Komatsu/McHale, had also been concluded.

The 8 April 2026 quarterly update put cash reserves at £25.5m as at 31 March 2026 and recorded tungsten sales Revenue of just £0.6m for the financial year to that date — the company remains pre-revenue in any meaningful sense until the plant is running. For context on the losses inherent in a pre-production developer, Tungsten West had earlier reported a widening pre-tax loss (£22.18m for the prior financial year) as Hemerdon work continued.

On operational scale, the company has referenced a nameplate throughput of around 500 tonnes per hour at full commissioning, though detailed steady-state production, recovery and cost figures were not restated in the recent commissioning-focused announcements.

What Could Drive the Shares Next

The clearest near-term catalyst is delivery against the commissioning calendar: first concentrate from the fines gravity circuit, followed by the coarse circuit and the new-build front end. Each milestone met on time and on budget de-risks the story and supports the Market Value — the shares traded around 42p in mid-August 2026, capitalising the company at roughly £520m on about 1.25bn shares in issue.

The second driver is completion of the up-to-US$85m debt facility, which would firm up the Balance Sheet and reduce reliance on the bridging loan. The third is the tungsten price itself. The company's feasibility study assumed an APT (ammonium paratungstate) price of US$400 per metric tonne unit; management cited a materially higher prevailing price at 31 March 2026, reflecting acute tightness in tungsten markets as Chinese export controls squeezed Western supply. Tin has likewise been quoted well above the study assumption. If those elevated prices persist through the ramp, Hemerdon's cash-generation potential looks far stronger than the base case envisaged.

Risks Investors Should Watch

Restarts are rarely linear. Hemerdon's own history — Wolf Minerals' failure — is a reminder that commissioning risk, throughput shortfalls and recovery disappointments can quickly erode economics. A slip in the Q1 2027 target, or a ramp that stalls short of nameplate, would pressure both sentiment and funding headroom.

Financing is the second risk. Definitive documentation on the larger debt facility had not been reported as fully signed as of the May update; any delay leaves the balance sheet leaning on a relatively expensive bridge. Dilution is a live consideration given the company's earlier Equity raises. Third, the Commodity tailwind cuts both ways: the current article's tungsten and tin prices appear far above historical norms, and a normalisation would compress margins. Finally, tungsten pricing references quoted by the company are notably above typical market levels and should be treated as company-stated figures rather than independently verified benchmarks.

Outlook

The next 6-9 months should be defining. If Tungsten West hits its staged milestones, Hemerdon would move from perennial development story to producing asset in a market structurally short of Western tungsten. Steady-state production is expected to follow into the second half of 2027, though that timing is an expectation rather than firm guidance. Delivery, not ambition, is now the test.

Final Take

Tungsten West has crossed an important threshold: recommissioning has physically begun, and the company is guiding to full commissioning in early 2027. With a strong commodity backdrop and funding largely lined up, the reward case is clear — but so are the execution and financing risks that have tripped up Hemerdon before. Investors will want to see milestones met on time and on budget before treating the restart as a settled outcome.