Key Highlights

  • Tungsten West is progressing a phased restart of the Hemerdon tungsten and tin mine in Devon, targeting full commissioning in Q1 2027.
  • The US Export-Import Bank has issued a non-binding letter of interest for up to $95 million under its Supply Chain Resilience Initiative.
  • A $25 million bridging Loan was secured in May 2026, with an $85 million Debt package in final documentation to partially refinance it.
  • Half-year results to 30 September 2025 showed no Revenue and a pre-tax loss of £40.4 million, driven largely by finance costs.
  • Tungsten and tin prices are trading well above the assumptions used in the company's feasibility study.

With tungsten prices near record highs and Washington eyeing the Devon mine as a source of critical minerals, Tungsten West has lined up bridge funding and a larger debt package to bring Hemerdon back into production by early 2027.

Few LSE-listed companies have had a year quite like Tungsten West. A year ago the owner of the Hemerdon tungsten and tin mine in Devon was a speculative restart story, its shares in single-digit pence. Today, with tungsten prices at multi-year highs, a US export-credit agency circling with a potential nine-figure loan, and a phased restart under way on site, the stock trades around 38p, valuing the company at roughly £474 million. The question is whether Hemerdon can convert that momentum into an operating mine — and whether the financing needed to get there is as close as it suggests.

What Happened

Hemerdon has a chequered history. Previous operator Wolf Minerals brought the deposit into production in 2015 but never hit its targets, ceasing trading in October 2018. Tungsten West floated on AIM in October 2021, took control and altered the processing plant, running interim operations from 2023.

The past year has brought a run of significant announcements. In August 2025 the company published a feasibility study for a full restart and, days later, revealed a non-binding letter of interest from the US Export-Import Bank (EXIM) for up to $95 million, under EXIM's Supply Chain Resilience Initiative aimed at securing critical mineral supply chains outside China. Shares jumped more than 30% on the news. In May 2026 it confirmed a $25 million unsecured bridging loan from an entity controlled by Gregory Coffey, a substantial Shareholder , while a larger $85 million debt package moved into final documentation, intended to partially repay the bridge loan.

Why It Matters

Hemerdon is one of the largest tungsten deposits outside China, and the company has said the project could ultimately supply around a fifth of global primary tungsten output excluding Chinese production. That matters as Western governments and manufacturers, particularly in defence and industrial tooling, look to diversify away from a China-dominated supply chain. EXIM's interest — even at the non-binding letter stage — signals US policymakers see the mine as part of a broader critical-minerals resilience effort, not just a niche UK Mining story. For a company that has repeatedly needed fresh Capital since 2021, that interest, alongside a supportive price backdrop, is the clearest external validation it has had.

Latest Financial and Operational Performance

Tungsten West remains pre-production by most measures. Half-year results to 30 September 2025, published in December 2025, showed no revenue and a pre-tax loss of £40.4 million, up sharply from £13.9 million a year earlier, driven largely by net finance costs of £36.6 million as debt and restart obligations have grown. By 31 March 2026 the company reported cash of £25.5 million and unaudited tungsten sales of around £600,000, an early sign of concentrate reaching market ahead of full commissioning.

Operationally, the restart is proceeding in phases. The fines gravity circuit is targeted to begin commissioning in Q3 2026, initially processing up to 100 tonnes an hour against an eventual capacity of 200 tonnes an hour, followed by the coarse gravity circuit in Q4 at around 150 tonnes an hour. Full commissioning, targeting nameplate capacity of 500 tonnes an hour, is due in Q1 2027, with output ramping through that year. The company is also building its workforce, with more than 120 new staff expected on site by end-June 2026, alongside new Komatsu equipment funded through a separate £22.3 million finance agreement.

Key Numbers

  • Share price around 38p; market cap roughly £474 million (7-8 August 2026); 52-week range 7.75p to 45.00p
  • $25 million unsecured bridging loan (May 2026), priced at SOFR plus 4.5% (about 8% initially), stepping up 1% a quarter, repayable within 366 days
  • $85 million debt package in final documentation, intended to partially refinance the bridge loan
  • Up to $95 million non-binding EXIM letter of interest (August 2025), with a maximum 15-year repayment structure under consideration
  • Cash of £25.5 million and unaudited tungsten sales of about £600,000 as of 31 March 2026
  • H1 FY26 (to 30 September 2025) pre-tax loss of £40.4 million on zero revenue; net finance costs £36.6 million
  • Tungsten prices above $3,000 per tonne unit and tin above $46,000 a tonne (March 2026) — both well ahead of feasibility-study assumptions

Growth Opportunities

The most obvious opportunity is getting Hemerdon into steady-state production while tungsten and tin prices remain unusually strong. A phased restart on schedule would give Tungsten West its first meaningful revenue from Q3 2026, with full commissioning in Q1 2027 unlocking the mine's designed 500 tonnes-an-hour throughput. A completed $85 million debt package, and any progress converting EXIM's letter into a binding Facility , would de-risk funding and could lower the Cost of Capital versus the shorter-dated bridge loan now in place. Growing Western appetite for non-Chinese critical mineral supply could also support offtake terms and pricing over time.

Risks Investors Should Know

Tungsten West still has no Operating Revenue of scale and a widening loss driven by rising finance costs. The $85 million debt package is being finalised, not signed, and the EXIM letter is explicitly non-binding — neither is secured funding until confirmed by RNS. Restart timelines in mining are prone to slippage, and Hemerdon's history under Wolf Minerals, which failed to hit targets before ceasing trading in 2018, is a reminder that commissioning a reopened plant carries real risk. Prices well above feasibility-study assumptions could also normalise, and 72.4% of shares are not in public hands, a concentration that can affect Liquidity .

What to Watch Next

Watch for confirmation that the $85 million debt package has been signed, any binding agreement following the EXIM letter, and progress on fines gravity commissioning through Q3 2026. Subsequent RNS updates on coarse circuit commissioning, workforce build-out and actual versus targeted throughput will show whether the Q1 2027 target is holding.

Outlook

Tungsten West has moved from a speculative restart story to one with tangible construction progress, early revenue and serious institutional financing interest. The Q1 2027 target is credible on current guidance, but it depends on debt facilities not yet finalised. For a market that has already re-rated the shares substantially, the coming quarters will show whether Hemerdon can finally deliver the production Wolf Minerals could not.