Key Highlights
- Hemerdon began phased commissioning from mid-2026 (fines circuit Q3 2026, full commissioning targeted Q1 2027) - not yet in commercial production.
- AIM trading is active; the October 2024 suspension (delayed audited accounts) was historical and resolved.
- A ~£44.4m raise at 18p (Feb 2026) plus a US$25m bridging Loan funded the restart's first phase.
- A larger Debt package of up to US$85m was in final-stage Due Diligence but unsigned; a US EXIM letter of interest (up to US$95m) is non-binding.
- Tungsten prices have surged on Chinese export controls; management says Hemerdon could Supply ~20% of primary tungsten outside China.
Tungsten West (LSE:TUN) is attempting one of the more ambitious restarts in UK mining: bringing the Hemerdon tungsten-and-tin mine in Devon back into production at a moment when tungsten - a critical metal for defence, tooling and electronics - has surged in price amid Chinese export controls. As at late August 2026 the company confirmed that phased commissioning of Hemerdon's processing plant had begun, marking the transition from a long financing-and-permitting saga towards operational reality.
The strategic backdrop is compelling: management says Hemerdon could supply roughly 20% of global primary tungsten from outside China, giving it genuine supply-chain-security relevance for Western governments. But investors should be clear-eyed - Tungsten West remains a development-stage, loss-making company that is commissioning, not yet commercially producing, and its funding package is not fully secured.
Latest Development
The pivotal recent catalyst is the start of phased commissioning. Following a July 2026 update, the company began commissioning the fines gravity circuit and Downstream processing in the third quarter of 2026, with the coarse gravity circuit scheduled for the fourth quarter and full plant commissioning targeted for the first quarter of 2027, ahead of a ramp towards nameplate throughput of around 500 tonnes per hour during 2027.
This has been enabled by an intensive financing effort. In February 2026 Tungsten West raised approximately £44.4 million via a placing, subscription and an oversubscribed retail offer priced at 18 pence per share.
The Numbers
As a pre-production developer, Tungsten West's financials reflect Investment rather than earnings: it has reported widening losses as restart costs rose, negative Operating Cash Flow and, at its 2025 year-end, negative shareholders' Equity - the balance-sheet strain typical of a project on the cusp of production.
The market backdrop has moved sharply in the project's favour. Tungsten (APT) prices have risen dramatically to multi-year highs, well above the assumptions in the original Hemerdon feasibility work, driven by Chinese export restrictions; tin has also traded strongly, above US$46,000 per tonne. Tungsten West arranged around £22.3 million of mining-equipment finance with McHale (Komatsu).
The Investment Story
Hemerdon is a genuinely strategic asset, hosting one of the world's largest tungsten resources. Tungsten's hardness and high melting point make it critical for cutting tools, armaments, aerospace and electronics - a market long dominated by China. Western moves to de-risk critical-mineral supply chains have transformed the case for a domestic, non-Chinese source, the narrative underpinning EXIM's interest and offtake discussions. Tin, a co-product, adds a second in-demand critical metal to the Revenue mix.
The investment story is therefore a high-conviction, high-risk restart play: if commissioning succeeds and the larger debt package closes, Tungsten West could become a meaningful Western tungsten supplier into a structurally tight market at attractive prices. The edge is location and strategic relevance rather than being the lowest-cost producer; Hemerdon has a chequered history (a previous operator entered administration), so execution through commissioning and ramp-up is the crux. This is a project moving from promise towards proof.
What Could Drive the Shares?
The clearest potential catalysts are financing and operational milestones: signing the up-to-US$85 million definitive debt package would remove a major overhang, and any firming of the EXIM Facility or binding offtake agreements would reinforce the strategic thesis. Successful commissioning of the fines and then coarse gravity circuits, followed by first saleable concentrate and a ramp towards nameplate capacity, would be the key operational proof points.
The Commodity backdrop is a powerful potential tailwind: with tungsten prices elevated on Chinese export controls, Hemerdon's Economics look far more favourable than at feasibility. Confirmation that costs and recoveries are tracking plan, and progress towards positive operating cash flow, could materially change how the market values the company.
Risks Investors Should Watch
This is a speculative, pre-production situation and the risks are substantial. Funding risk is paramount: the larger US$85 million debt package was not yet signed at the time of the update, and the company is reliant on a bridging loan and prior equity raises; further dilution or delay cannot be ruled out, and the group has reported negative shareholders' equity. Commissioning and ramp-up risk is real - process plants frequently underperform initially, and Hemerdon's prior operator failed.
What Happens Next?
The near-term milestones are well defined: commissioning of the fines gravity circuit and downstream processing in Q3 2026, the coarse gravity circuit in Q4 2026, and full plant commissioning targeted for Q1 2027, with a ramp towards nameplate throughput through 2027. Investors should watch closely for the signing of the definitive US$85 million debt package, any conversion of the EXIM letter of interest into a committed facility, binding offtake agreements, and the first announcement of saleable tungsten (and tin) concentrate.
Bottom Line
Tungsten West (LSE:TUN) offers a rare Western tungsten restart at a moment of acute supply-chain focus and elevated prices - a genuinely strategic proposition. The bull case is that commissioning succeeds, the larger debt package and offtakes close, and Hemerdon becomes a significant non-Chinese tungsten source with strong economics. The risk case is equally clear: the company is still pre-production, loss-making, reliant on unsigned debt and prior dilutive raises, and must navigate commissioning at a site with a difficult history. This is a high-risk, milestone-driven story where the strategic upside is real but the execution and funding hurdles are not yet cleared. Not for the risk-averse.
What to Watch
- Signing of the definitive up-to-US$85m debt package and repayment of the bridging loan.
- First saleable tungsten/tin concentrate and progress of the commissioning ramp towards nameplate capacity.
- Conversion of the EXIM letter of interest into a committed facility and any binding offtake agreements.
- Any further equity raises or dilution given negative shareholders' equity and ongoing losses.
- Tungsten (APT) and tin price trends and Chinese export-policy developments.