Highlights

• Heavy earthmoving equipment is clearing access to the first three planned processing-plant locations at Walviskop.

• SAI expects its 30-container equipment shipment in November 2026, supporting a phased production start in early 2027.

• WHM operatives will transfer to SAI in three phases between end-November 2026 and end-January 2027.

• A US$1.75m payment from SAI stands ready, pending final registration of the 2A Mining Right.

Between now and early 2027, Kazera Global (LSE:KZG) has a closely sequenced calendar in South Africa. Ground is already being cleared at Walviskop, equipment is due to land this month, staff are moving across in stages and a US$1.75m payment is waiting on one final registration step.

Site preparation under way at Walviskop

The update from Kazera Global (LSE:KZG) says site preparation has started at Walviskop. Heavy earthmoving work is opening up access to the first three planned processing-plant locations, laying the groundwork for the equipment that follows.

Equipment shipment and production timetable

SAI's equipment shipment of 30 containers is due in November 2026. That delivery supports a phased production start, which is targeted for early 2027.

Under the arrangements described in the update, WHM retains a 20% production entitlement on a cost-free basis.

Phased transfer of WHM operatives

The update sets out a staged move of WHM operatives to SAI, intended to reduce WHM's operating costs. The schedule runs as follows:

• three operatives by the end of November 2026

• three more by the end of December 2026

• a further eight to nine by the end of January 2027

Regulatory steps and the US$1.75m payment

In the Kazera Global (LSE:KZG) update, two regulatory milestones have been completed. The NNR carried out an inspection on 8 and 9 September 2026, and an independent radiation audit followed on 5 November 2026. Waste reports were accepted.

A payment of US$1.75m from SAI is ready to be made. Its release is pending the final registration of the 2A Mining Right.

Understanding the Moving Parts

The update describes several linked activities at Walviskop. Site preparation is under way, with heavy earthmoving opening up access to the first three planned processing-plant locations. A shipment of 30 containers of equipment from SAI is due in November 2026, and a phased production start is targeted for early 2027. Under the arrangements described, WHM retains a 20% production entitlement on a cost-free basis, which means it receives that share of production without bearing costs.

Staff Transfers and Regulatory Milestones

WHM operatives are to move to SAI in stages, with three by the end of November 2026, three more by the end of December 2026 and a further eight to nine by the end of January 2027. The update says the move is intended to reduce WHM's operating costs. On regulation, the NNR carried out an inspection on 8 and 9 September 2026, and an independent radiation audit followed on 5 November 2026, with waste reports accepted. The NNR is the South African regulator responsible for nuclear matters, and its involvement reflects the nature of the material being handled at the site. These two milestones have been completed, so regulatory work forms part of the progress described.

The Payment and Next Steps

A payment of US$1.75m from SAI is ready to be made, and its release is pending the final registration of the 2A Mining Right. A mining right is the legal authority to extract minerals from a defined area, and registration is the formal step that records it. The update therefore links the payment to a defined legal step rather than to any further technical work. For readers following Kazera Global, the main items to follow are the arrival of the equipment in November, the progress of earthmoving, the staged transfer of operatives, the registration of the mining right and the targeted early 2027 production start. Each of those items has a date or condition in the update, which gives a clear sequence for the period between now and the start of production. The update does not give production volumes or financial projections, so later announcements will be needed for those details.