Beyond this year's numbers

Anglo Asian Mining (LSE:AAZ), which produces copper, gold and silver in Azerbaijan under a production sharing agreement with the government, has issued no news since a 3 November notice confirming the sterling value of its interim dividend. With the near-term focus on whether the Demirli mine reaches steady state, it is worth examining the longer path the company has set out: becoming a mid-tier, mainly copper producer by 2030. All figures are in US dollars, the company's reporting currency.

The stated target

The company (LSE:AAZ) says it expects annual copper output of around 50,000 to 55,000 tonnes by 2030, by bringing three more mines into production between 2027 and 2030 at Xarxar, Garadag and Zafar, in addition to Gilar and Demirli, which started in 2025. For context, guidance for 2026 is 20,000 to 25,000 tonnes, and output in the nine months to 30 September was 14,354 tonnes. The company said Xarxar and Garadag are on track to enter production in 2028 and 2029 respectively. At 30 June, the company said Gilar, Zafar, Xarxar and Garadag together held JORC-compliant mineral resources, across measured, indicated and inferred categories, of more than one million tonnes of copper and over 300,000 ounces of gold. Demirli also hosts a significant copper resource outside JORC reporting.

What must happen first

Engineering group Worley was appointed in June to carry out feasibility studies for both deposits. According to the interim results of 21 September, the Xarxar study is expected in the second half of 2027 and the Garadag study in the first half of 2028. That leaves a short window between study completion and the targeted production dates, implying construction decisions, financing and permitting would need to follow quickly.

Alongside the studies, the company (LSE:AAZ) is testing processing routes. A heap leach test pad and a solvent extraction and electrowinning pilot plant at Gedabek will treat about 10,000 tonnes of Xarxar ore, a tunnel at Garadag is being built to pilot underground in-situ leaching, and a laboratory is testing biological leaching. Open pit mining has been chosen as the preferred method at Garadag. A 90,000-metre core drilling programme runs through 2026 and 2027.

The Royalty question

Revenue from Gedabek and Demirli carried an effective royalty of 12.75% in the first half. The company expects that rate to continue at Demirli until at least the end of 2026 but to rise to around 18% at Gedabek by the end of this year. A move of roughly five percentage points on Gedabek Revenue would reduce the share retained by the company, all else equal, although the effect depends on metal prices and volumes from that contract area. First-half All-In Sustaining Cost for group copper was $5,158 a tonne, below full-year guidance of $6,000 to $7,000.

Why it matters now

The Balance Sheet gives the company room to fund early-stage work. Net cash was $47.1m at 30 September, after a $30.1m Working Capital build tied to September sales, which the company expects to reverse in the fourth quarter. First-half revenue was $141.2m and pre-tax profit $68.5m. The board has said it is drawing up a formal capital allocation policy, which will need to balance dividends against development spending.

Factors to watch and what comes next

Gold guidance was cut to 26,000 to 30,000 ounces because of variable recoveries from Gilar ore, a reminder that metallurgy can vary. Development timelines in the region depend on government approvals, including a new tailings Facility at Demirli. The 6 US cent Interim Dividend is payable in November to holders on the register at 6 November. The company expects Demirli to reach steady-state production by the end of November, and the date of the next quarterly production update has not yet been announced.