Permits in hand, drilling funded
First Development Resources (LSE:FDR) has moved its Selta project in Australia's Northern Territory from permitting into drilling. On 27 April 2026, the company announced that it had received a Notice of Authority to Commence Mining Activities, following the grant of Environmental (Mining) Licence EML 32755. It said the associated security bond had been lodged and accepted, clearing the way for a first phase of Reverse Circulation Drilling at the Lander West gold target.
In June 2026, the company then separately reported that it had won an AU$100,000 grant under the Northern Territory Government's Geophysics and Drilling Collaborations programme. Drilling was scheduled for July 2026.
The Lander West target
The initial campaign was described as comprising about 2,000 metres of drilling, with scope to extend to 3,000 metres. It was presented as the first substantial test of gold mineralisation below 50 metres along the Stafford Gold Trend at Lander West.
The grant was described as fully covering the initial phase. In our analysis, the grant is meaningful for a company of this size because it reduces the immediate need to issue new shares for the first holes, but it is modest relative to the cost of the multi-stage drilling that would be needed to define a resource.
The wider portfolio
First Development Resources is an early-stage explorer. It holds eight granted, wholly owned tenements covering 2,314.4 square kilometres. Five are in Western Australia, where the focus is copper-gold, and three are in the Northern Territory, where the company describes the Selta ground as prospective for gold, rare earth elements, uranium, lithium and base metals.
A broad Commodity list is common among junior explorers at this stage, reflecting geology that has not yet been fully tested rather than confirmed deposits.
In our assessment, the practical effect is that the company's near-term news flow is likely to be dominated by Lander West. The Western Australian copper-gold ground offers a second avenue, but a small explorer's budget typically has to be concentrated on one priority target at a time, so progress on the other tenements may be slower until the outcome of the Selta drilling is known and further funding is secured.
Share price and valuation
On 30 September 2026 the shares were priced at 1.75p, giving a Market Capitalisation of about GBP 2.4 million. Trailing Diluted Earnings per Share stood at minus GBP 0.0127, and no Dividend is paid.
Sector context
Gold exploration activity in Australia has been supported by high gold prices, and state and territory co-funding schemes exist to encourage drilling in under-explored regions. The Northern Territory's collaboration programme is one such scheme. Such grants are awarded on technical merit, but they do not, by themselves, indicate that a project will prove economic.
Risks and uncertainties
The central risk is geological, as in all early exploration: first-pass drilling frequently fails to return economic intercepts. Beyond that, as is typical in the sector, a company with a Market Value of a few million pounds is likely to need further funding to follow up any success, which could dilute existing shareholders. Remote Northern Territory operations can also be affected by wet-season access, contractor availability and assay turnaround times.
What to watch next
Readers may wish to follow confirmation that the Lander West drilling has been completed, the timing and content of assay results, whether the programme is extended towards 3,000 metres, any activity on the Western Australian copper-gold tenements, and the company's cash position and any further fundraising in its next accounts.