Kore Potash (LSE:KP2) has published its review of operations for the quarter ended 30 September 2026, reporting cash of about USD 6.4 million, continued work on the Mining Convention for its Kola potash project in the Republic of Congo, and two parties engaged in its Formal Sale Process.
Kore Potash quarterly review: what was announced
In its quarterly operational review, the AIM-quoted potash developer said activity during the quarter centred on clarifying how its Mining Convention for the Kola project applies under the Republic of Congo's new Mining Law, Law No. 1-2026 of 18 April 2026. Chief executive André Baya said: "Activities in the third quarter have largely focused on clarifying the position of the Mining Convention relative to the new Mining Law in the RoC." The company described this work as essential to enable its Formal Sale Process to proceed.
Cash at 30 September 2026 stood at about USD 6.4 million. Exploration Investment in the quarter was USD 662,000, of which USD 659,000 related to the Kola study and USD 3,000 to the Dougou Extension definitive feasibility study. No mining production or construction took place.
Why Kola matters to UK shares investors
Kola is the company's flagship project, and Kore reports gross JORC 2012 Ore Reserves of 152 million tonnes at 32.5% KCl for the Kola sylvinite deposit. Mr Baya said: "Kola is a globally significant potash project with a team intent on driving it towards production."
Validation tests in China produced concentrate grading 96.91% KCl, a 3.12-point improvement on the 2018 result, with recovery of 83.46%, essentially unchanged. The beneficiation-test condition has been satisfied. Front-end engineering design for shaft and underground works continues. The originally specified vertical conveyor system is no longer manufactured, so an alternative requires minor redesign.
Formal Sale Process and financing context
The Formal Sale Process began on 4 November 2025. Kore said two parties are engaged, both evaluating an Acquisition of the company's entire issued and to-be-issued share capital. One earlier party withdrew on 27 February 2026, and a new party approached the company on 8 June 2026. The release does not describe any firm or possible offer.
On funding, Kore signed non-binding term sheets with a prospective funding partner on 10 June 2025 covering the total funding requirement for Kola. Discussions continue with a prospective strategic partner that would both invest in the company and operate the mine. The company is also considering strategic Options for the Dougou Extension project.
Risks flagged in the update
The Mining Convention requires construction to start by 8 June 2027, and Kore said discussions with the government on formalising the way forward are continuing. The environmental and social impact assessment, resumed in April 2026, was suspended at the end of May 2026 pending the sale process. The funding partner term sheets are non-binding, and there is no certainty that the sale process will result in an offer. The government's 10% interest in the local project companies is being transferred to the Ministry of Finance, with the legal process ongoing.
What investors may watch next
Market participants may look for progress on formalising the Mining Convention position, developments in the Formal Sale Process, confirmation of design changes from strategic investors that would allow ESIA work to resume, and the hoisting system redesign.
The quarter was one of groundwork rather than construction, with legal clarity, the sale process and financing all central to Kola's next steps. Mr Baya said: "The remainder of 2026 promises to be a highly significant one for Kore."