Bazalgette Finance plc (LSE:38LO) has published an FCA-approved prospectus updating its £10 billion multicurrency bond programme, alongside a project update in which Tideway now expects System Acceptance of the Thames Tideway Tunnel between February and August 2028. Ofwat has said it does not intend to impose financial penalties for the weather-related delay.
What was announced
On 25 September 2026, Bazalgette Finance plc (LSE:38LO), the programme issuer for Tideway, announced the publication of a prospectus dated 25 September 2026 relating to the update of its £10,000,000,000 multicurrency programme for the issuance of bonds. The prospectus has been approved by the Financial Conduct Authority.
Although the announcement's headline refers to a launch, the announcement describes the document as an update of the existing programme rather than the creation of a new one. The guarantor named in connection with the programme is Bazalgette Tunnel Limited, referred to in the announcement as Tideway.
The announcement does not specify the classes of bonds, Credit ratings or the listing venue, and publication of the prospectus does not in itself mean any bonds have been issued.
The project update
Alongside the prospectus, the company provided an update on the Thames Tideway Tunnel (TTT).
In August 2026, Tideway achieved Handover, which the company described as "a significant milestone marking the commencement of the System Acceptance phase and the transfer to Thames Water of responsibility for operating the TTT." Responsibility for day-to-day operation of the tunnel therefore now sits with Thames Water.
The next milestone, System Acceptance, has been delayed. The original Planned System Acceptance Date (PSAD) was 31 August 2027. Tideway now expects System Acceptance "to occur between February 2028 and August 2028, depending on when the applicable acceptance criteria are satisfied." On the dates given, this represents a delay of roughly six to twelve months against the original PSAD.
Reasons for the delay and the regulatory position
Tideway attributed the delay to weather. According to the announcement, prolonged periods of dry weather and reduced inflows following the connection of the tunnel constrained commissioning activities.
Ofwat, the water regulator, "has confirmed that it does not intend to impose financial penalties in respect of the weather-related delay." The announcement adds that discussions are ongoing regarding potential amendments to the regulatory framework to reflect the revised timetable, including an amendment to the PSAD and an increase to funding. The size of any funding increase, and the timing of any decision, were not disclosed.
Cost and performance
The company's revised cost estimate as at 31 August 2026 remains £4.7 billion, meaning the delay to System Acceptance has not, on the company's figures, changed the overall cost estimate. The announcement does not break down the estimate, or explain how it relates to the increase in funding under discussion with Ofwat.
Tideway also reported that, as at 15 August 2026, more than 21 million cubic metres of sewage had been diverted from the River Thames by the tunnel. The announcement does not provide further operating or financial figures, such as regulatory Capital value, Debt levels or gearing.
What to watch next
The main items to follow are the outcome of discussions with Ofwat on amending the PSAD and on any increase to funding, and progress towards meeting the acceptance criteria within the February to August 2028 window. Investors in the programme may also look for any issuance under the updated prospectus and for any further change to the £4.7 billion cost estimate as the System Acceptance phase continues.
The full prospectus contains the programme's terms and risk factors, which are not summarised in the announcement itself.