Key Highlights
- First-quarter adjusted networks Investment reached £888m, up 83%, with £666m going into transmission.
- Renewables output rose 31% to 3,264 GWh, helped by a near-doubling of hydro, pumped storage and battery output.
- FY2026 adjusted Earnings Per Share were 153.5p, with guidance of 168-193p for the current year.
- The full-year Dividend was lifted 7% to 68.7p, with capex expected to exceed £5bn this year.
SSE PLC (LSE:SSE) has just spent a day walking investors around substations and cable landing sites in Aberdeenshire, and the message was deliberately unexciting: no new numbers, no new targets, just evidence that a £29bn transmission programme is physically being built. For a FTSE 100 Utility that raised £2bn from shareholders last November to fund a £33bn five-year plan, that tone is the point.
The question is whether SSE can keep converting Britain's grid-upgrade policy into regulated asset growth and earnings at the pace promised. Full-year results in May showed adjusted earnings per share of 153.5p for the year to 31 March 2026, a dividend up 7%, and guidance for 168–193p this year. With a trading update due on 30 September, delivery is now the story that matters.
Investor event and Q1 update: transmission spending nearly doubles
The most recent announcement came on 2 September 2026, when SSE hosted an Investor relations event in Aberdeen dedicated to SSEN Transmission. Managing director Rob McDonald and his team presented progress on the £29bn RIIO-T3 investment plan, with site visits to Eastern Green Link 2 and the Netherton Hub near Peterhead. SSE stated that "no material new financial information or new targets will be shared at the event", so the significance lies in visibility on delivery.
The harder numbers came in the Q1 trading statement of 16 July 2026, covering the three months to 30 June. Adjusted networks investment reached £888m, up 83% from £484m a year earlier, with £666m going into SSEN Transmission. Renewables output rose 31% to 3,264 GWh, helped by a near-doubling of hydro, pumped storage and battery output. Dogger Bank B had 30 turbines installed and Netherton Hub construction had begun.
Chief financial officer Barry O'Regan said: "Since announcing our £33bn investment programme... we are continuing to see real progress as we work to deliver", pointing to "increased visibility over the delivery of our 2030s pipeline". That visibility improved on 30 June, when the National Energy System Operator's "Beyond 2030 Update" identified more than £12bn of additional north-of-Scotland reinforcements, including two new 2GW HVDC links, lifting potential spend under RIIO-T3's uncertainty mechanism to more than £17bn, subject to approvals.
Business overview: networks, renewables and flexible generation
SSE is a Perth-headquartered energy group whose Business now tilts heavily towards regulated electricity networks. SSEN Transmission owns and operates the high-voltage grid across the north of Scotland, the region carrying much of Britain's wind power south, while SSEN Distribution runs lower-voltage networks in central southern England and northern Scotland. Both earn returns on a regulated asset value (RAV) set by Ofgem; the RIIO-T3 settlement, accepted on 2 March 2026, runs from April 2026 to March 2031.
Alongside networks, SSE Renewables develops and operates onshore and offshore wind, hydro and pumped storage, including its stake in Dogger Bank. SSE Thermal runs flexible gas-fired plants, Energy Customer Solutions serves business customers in Great Britain and Ireland, and SSE Energy Markets handles trading. Roughly 80% of the £33bn plan to 2029/30 is earmarked for networks, with about 12% for renewables and 6% for thermal.
Full-year results: record capex, earnings dip, dividend up 7%
Preliminary results for the year to 31 March 2026, published on 28 May 2026, showed adjusted operating profit of £2,236.6m, down 8%, as growth in transmission (up 75% to £562.6m) and renewables (up 4% to £1,076.4m) was offset by a 54% fall in distribution profit to £335.3m and a 29% decline in customer solutions. Adjusted profit before tax fell 6% to £2,024.8m and adjusted EPS slipped 5% to 153.5p, beating the 147–152p range guided in April. Reported profit before tax was £1,837.3m and reported EPS 105.5p.
Investment and Capital Expenditure hit a record £3,585.6m, up 23%, with 48% deployed in transmission. Adjusted net Debt and hybrid capital was flat at £10.1bn, with net debt to EBITDA of 3.3 times, and gross networks RAV rose to £15.6bn from £12.9bn. The full-year dividend was lifted 7% to 68.7p, comprising a 21.4p interim and a 47.3p final payable on 17 September 2026. At the 2,372p share price shown on SSE's investor page on 2 September, that equates to a Yield of roughly 2.9%.
Chief executive Martin Pibworth said: "We met all our financial and operational targets and delivery of our fully-funded £33bn investment plan to 2030 is well under way." Guidance is for adjusted EPS of 168–193p in 2026/27 and 225–250p in 2029/30, with capex expected to exceed £5bn this year and the dividend to grow by 5–10% a year from a 64.2p base.
What could drive the stock next?
The next scheduled marker is the 30 September trading update. Investors will watch whether the £5bn capex target and the 168–193p EPS range hold after the weather-dependent summer months. Beyond that, regulatory approval of the additional £12bn of NESO-identified projects would extend SSEN Transmission's growth well into the 2030s.
Renewables offer their own milestones. Berwick Bank B secured a 20-year contract for difference at £89.49/MWh in Allocation Round 7, announced in the February Q3 statement, and a final investment decision on that 1.4GW project would be a notable step. Commissioning of Dogger Bank A, the ramp at Dogger Bank B and Ofgem's "minded-to" support for the Coire Glas pumped-storage scheme also sit in the pipeline.
Risks investors should watch
The scale of the programme is itself the main risk. Delivering more than £5bn of capex a year across 11 major transmission projects, wind farms and gas plants leaves room for cost inflation, supply-chain delays and consenting setbacks, even with 26 of 34 consents secured by April. Any slippage would push out RAV growth and the earnings guidance built on it.
Funding is the second concern. SSE has already tapped shareholders for £2bn and raised £2.4bn of hybrid and senior debt in the first quarter alone, with Leverage at 3.3 times EBITDA. Higher interest costs or a ratings downgrade would raise the price of that capital, and the group remains exposed to Ofgem's decisions on allowed returns and to political intervention in network charging.
Earnings also remain sensitive to weather and power prices. The 2025/26 EPS decline shows how a weak year in distribution or customer solutions can offset growth elsewhere, and the company flagged in April that it "continues to closely monitor developments in the Middle East".
Outlook
The SSE (LSE:SSE) investment case has become simpler and more regulated over the past year: a 2031 transmission settlement is in hand, the funding is raised, and the first quarter showed spending accelerating on schedule. The trade-off is that shareholders have accepted dilution and a dip in near-term earnings for a promised 10–13% compound EPS growth to 2029/30.
The 30 September trading update, the Berwick Bank investment decision and Ofgem's treatment of the extra £12bn of transmission projects are the near-term signposts. If the numbers keep tracking guidance, the site visits in Aberdeen may prove more persuasive than any new target.