The study behind the headline numbers

No new announcement from Mkango Magnetic Materials (LSE:MKA) appeared between 12 and 16 November, so this piece returns to the most substantial recent disclosure: the independent pre-feasibility study (PFS) on expanding HyProMag USA, published on 27 October 2026. The study, prepared by PegasusTSI and BBA USA, looks beyond the first plant at Northlake, Texas, and assesses three further regional plants plus a central finishing and alloy hub in Texas.

The company said the three new plants would carry a post-tax net present value of US$1,854m to US$2,062m, depending on whether they use recycled scrap only or also take primary alloy. Post-tax returns were put at 31% to 36%, against a Class 3 Capital cost estimate of roughly US$623m to US$656m. Including Northlake, the combined platform was valued at US$2.6bn to US$2.8bn, with saleable magnet output rising from about 1,048 tonnes a year to about 4,192 tonnes by 2034.

These are project-level figures, not values for Mkango shareholders. HyProMag USA is a 50:50 joint venture between CoTec Holdings and HyProMag Limited, which is wholly owned by Maginito. Mkango holds 79.4% of Maginito. That gives Mkango an effective economic interest of about 39.7% in HyProMag USA.

Applying that percentage mechanically, Mkango's (LSE:MKA) look-through share of the expansion NPV would be roughly US$736m to US$819m, and of the combined four-plant figure about US$1.0bn to US$1.1bn. The same calculation implies an attributable share of expansion capital of around US$247m to US$260m. These numbers ignore financing structure, future dilution, taxes above project level and the time value of reaching each stage, so they should be read as an upper-bound illustration rather than a valuation.

Northlake has to work first

Everything in the expansion case rests on the first plant. The updated Northlake NPV fell to about US$723m from US$797m stated in June, which the company attributed to a later construction timetable, higher capital costs and revised operating assumptions. Northlake's capital estimate now stands at roughly US$167m. Initial cutting and finishing is targeted for the first half of 2027, with integrated Phase 1 commissioning expected in mid-2028. On 9 November HyProMag USA reported delivery of the first major process equipment to the site.

Funding and simplification elsewhere

Mkango also announced on 9 November a proposed fundraising through AIM's Capital Access Window, with proceeds intended for recycling and magnet Manufacturing scale-up and working capital; no results announcement appeared in the company's announcement list by 17 November. Separately, on 28 October it agreed to buy the final 10% of HyProMag Germany for £1.06m, mostly in new shares at 29.5p, lifting its effective interest in the Pforzheim plant from 71.5% to 79.4%.

Assumptions and factors to watch

The PFS uses a 7% real discount rate, a 21% federal tax rate excluding state taxes, Adamas Intelligence price forecasts from the second quarter of 2026, and plant construction starting in 2030, 2032 and 2034. Its value excludes government incentives. Weighted realised prices of about US$100.5 per kilogram in 2030 compare with all-in sustaining costs of US$37.4 to US$41.6 per kilogram, so margins are sensitive to rare earth and magnet prices. Feedstock availability, customer qualification, permitting and financing remain open questions, and no carbon assessment has yet been completed for the new plants.

What to watch

Near-term markers are the outcome of the 9 November fundraising, completion of the HyProMag Germany share purchase, Northlake financing and the planned 2027 start of finishing operations. Mkango (LSE:MKA) said the expansion would move to a feasibility study at the appropriate time. Investors may look for offtake agreements, since the company said customer validation with potential US buyers is under way. Separately, the proposed Nasdaq listing of its Songwe Hill and Pulawy Assets via a SPAC Merger continues on its own track.