The latest disclosure

Kore Potash (LSE:KP2) has published no substantive news between 12 and 16 November 2026; its most recent announcement was a routine monthly report on depositary interests on 3 November. The last operational update was the review of operations for the quarter to 30 September, released on 30 October. Coverage has understandably centred on Congo's new Mining Law and the formal sale process. This piece looks instead at the technical workstreams that would need to be finished before construction of the Kola potash mine could begin.

For context, Kola's ore reserve, first stated with the 2019 feasibility study, stands at 152 million tonnes grading 32.5% potassium chloride on a gross basis, within a measured, indicated and inferred sylvinite resource of 848 million tonnes. Kore owns 97.58% of the project holding company, and the Congolese state is entitled to 10% of the operating subsidiaries, a stake the government has confirmed will be held by its Ministry of Finance.

Metallurgy: validation results

The quarterly review sets out validation testing carried out at ENFI's laboratories in China under the early works arrangements with PowerChina, the engineering, procurement and construction contractor. The tests aimed to replicate the 2018 definitive feasibility study flotation results using similar equipment and reagents.

According to the company, the combined concentrate graded 96.91% potassium chloride, 3.12 percentage points above the 2018 result, while combined recovery of 83.46% was essentially unchanged. First-pass rougher flotation performed better, at 96.17% grade and 85.85% recovery, against 93.85% and 78.55% previously, and locked-cycle tests stabilised after two cycles rather than eight. Kore (LSE:KP2) said the parties had agreed that the beneficiation test condition precedent in the early works agreement had been fully satisfied.

The results confirm rather than transform the process design: recovery, the variable most directly tied to output, is unchanged, but higher grade and faster stabilisation could help optimise the circuit, as the company suggested.

Shaft and hoisting redesign

Front-end engineering design for the shaft and underground mine is continuing between PowerChina and UMS. The company said changes were needed because the vertical conveyor system originally specified is no longer manufactured by ContiTech, part of Continental. One alternative has been identified, which Kore said would require minor redesign. It gave no estimate of the cost or of any schedule impact.

Environmental work and land

The update to the environmental and social impact assessment, required by design optimisations, has stalled twice. Environmental baseline data were completed in October 2025, but social baseline work was left incomplete in case a new investor requested design changes. Activity resumed in April 2026 after six months and was suspended again at the end of May pending the sale process. The social work feeds a resettlement plan needed for a government-led public Utility declaration, which is a prerequisite for the land to be made available.

Cash and dependencies

Kore (LSE:KP2) held about US$6.4m of cash at 30 September. It reported investing US$662,000 in exploration and studies during the quarter, almost all on Kola. That figure excludes corporate costs; the fuller Cash Flow report lodged with the ASX was not reviewed for this article.

The dependencies are interlinked. Investors in the sale process are expected to specify design changes, which in turn determine when environmental and resettlement work can finish. The Mining Convention requires construction to start by 8 June 2027, and financing from OWI-RAMS remains under non-binding term sheets signed in June 2025.

What to watch

Key markers are confirmation of the replacement hoisting design, a restart of the impact assessment, any formal agreement with the government on applying the Mining Convention, and the outcome of the sale process, in which two parties remain engaged. No date has yet been given for the next quarterly operations review.